
Marlborough Region Transitions To Recovery
The Notice of Local Transition period, under Section 94B of the Civil Defence Emergency Management Act 2002, took effect at 3.30pm today and ends on 1 August unless it is extended or ends before then.
Mayor Taylor extended her thanks to all the agencies, community groups and volunteers who had supported the Marlborough Emergency Management response and made special note of the advance warning given by Council's hydrology team of the potential impacts of the weather event.
Marlborough Emergency Management Group Manager and duty controller Matt Kerr said he had recommended the transition period due to record groundwater levels still affecting the region following the recent weather event and with impacts across the region still 'dynamic and emerging.'
'There is still a risk of ongoing impacts and consequences which may require us to manage, coordinate or direct recovery activities so this transition period is important to facilitate a timely and effective recovery from this event,' Mr Kerr said.
Group Recovery Manager Dean Heiford will now assume responsibility for the local transition period.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Scoop
2 hours ago
- Scoop
Nelson Tasman Region Transitions To Recovery
Tasman Mayor Tim King has given notice that Nelson Tasman will begin a transition period, moving from a state of emergency into a recovery focus, following the impacts from the severe weather the region experienced at the end of June 2025. The Notice of Local Transition period, under Section 94B of the Civil Defence Emergency Management Act 2002, took effect at 10.30am today (7 July 2025) and ends on 4 August 2025 unless it is extended or ends before then. Mayor King extended his thanks to all the agencies, community groups and volunteers who had supported the Nelson Tasman Emergency Management response. "This has been a profoundly damaging event, and we have seen major impacts across our region, especially in the Wai-iti and Motueka Valley catchments. While we are moving from a state of emergency, this transition period means that support continues to be available to those affected. "A big thank you to everyone involved, including those in our community who have supported and continue to support their friends, family and neighbours. "Our supporting agencies have once again stepped up, and responded to help our communities in need, and we want to extend our thanks to those who have provided support from outside of our region. " Nelson Mayor Nick Smith was encouraged by the shift to the transition period. "The timing is right for us to lift the State of Emergency and move to the transition phase. This event has hit Tasman much harder than Nelson but with the Rocks Road State Highway now open, Nelson is back to normal and open for business. "The recovery work for our Tasman neighbours is going to be long and hard, as it was for Nelson from the August 2022 event. We will be continuing to support Tasman and the rural community with the transition and recovery work. There are still risks for Nelson from any future heavy rainfall with the ground being so sodden, particularly from landslips, and we will need to be vigilant and keep a close eye on weather forecasts.' Group Recovery Manager Steve Manners will now assume responsibility for the local transition period.


Scoop
5 hours ago
- Scoop
Flood Protection Project Targets Vulnerable Area Of Nelson
A multi-million dollar project that will increase the flood carrying capacity of the Maitai River between Hanby Park and Clouston Terrace will get underway this summer. The most significant flood resilience project undertaken by Council since the Saxton Creek Upgrade, the work targets an area that saw some of the worst flooding during the August 2022 weather event. This area of the Maitai is particularly vulnerable to flooding, with the existing stopbank at Clouston Terrace currently only capable of withstanding a 1:50 year flood event. In August 2022, flooding affected properties between Nile Street, Mill Street and the stopbank. 'I have been involved with Civil Defence responses for 15 years. The flooding in this area in 2022 was some of the worst I have ever seen,' says Group Manager Infrastructure Alec Louverdis. This project will reduce the risk of future flooding in the area in five ways, including: New floodwalls Upgrading the quality of existing stopbanks Increasing the capacity of the river channel On Tuesday 24 June, Council held a community meeting with affected residents to present the project plan for the Maitai between Hanby and Clouston. 'This is exciting for us from a technical point of view, but also for the solutions developed by our specialist engineering consultants Tonkin & Taylor,' says Alec. 'We were encouraged by the positive and supportive response from residents and we will keep in close contact throughout the work. All were keen for the work to start as soon as possible.' Advertisement - scroll to continue reading Tonkin & Taylor looked out as far as 2130 and modelled solutions for a range of present day and future extreme weather scenarios. Their main focus was to maintain recreational access and the integrity of the river. 'Some solutions looked at potential property purchases but Tonkin and Taylor's innovative and practical design allows us to achieve the required outcomes without going down this avenue. The decision to take land from Hanby Park instead was a practical and compassionate solution and we're really happy with the outcome.' The summary of the proposed work includes: Lowering the level of the bank under the east bridge span creating more space under the bridge for pedestrians and cyclists. A 2m flood wall alongside the new pathway adjacent to Clouston Terrace, that will extend to chest height above the road carriageway. 'We are raising Clouston Terrace,' says Alec. 'Clouston Terrace, which runs alongside this section of the river may be raised by over a metre, as a result we will need to reconfigure several property accessways. We will be working with residents for the best solution for each property.' Once the project is complete, Council will work closely with residents to discuss options for enhancing the area, including opportunities for planting and artistic detailing of the concrete wall. These finishing touches are an important way to reflect the character of the neighbourhood and involve the community in shaping the final look and feel of the space. The project team recognise the importance of protecting the natural ecology both in and around the river. A lizard survey found the protected northern grass skink inhabits the Maitai River banks within the works area. Council has sought a Wildlife Act Authority permit from Department of Conservation to salvage the lizards and relocate them to the pest-free Brook Waimārama Sanctuary. Along with the local lizards, the Maitai is considered as a 'high' value habitat with a diverse native fish community. In-river construction will be timed to avoid the spawning season for bullies and trout, and erosion and sediment control measures will be in place to protect water quality and instream habitat. Where works in the water cannot be avoided, ecologists will capture and relocate fish away from the construction zone. Once completed the floodways will provide additional habitat for fish and planting will provide shade for fresh water species. For the local birds, works will be undertaken outside of bird breeding season where possible and bird nests will be checked prior to any removal of vegetation. Notes: Four individual projects make up the wider Maitai Flood Resilience project. This overall project includes stormwater intake upgrade on Cleveland Terrace, river flood improvements from Hanby Park to Clouston Terrace, a flood wall upgrade and extension on Nile Street and at stormwater improvements at Queens Gardens for a total budget of $9 million, for which we are receiving $5.4 million from Central Government through the Regional Infrastructure Fund. This work will be carried out over the next two financial years and completed by July 2027.


Scoop
3 days ago
- Scoop
Marlborough Region Transitions To Recovery
Marlborough Mayor Nadine Taylor has given notice that Marlborough will begin a local transition period due to the district-wide impacts from severe weather in the region over the past week. The Notice of Local Transition period, under Section 94B of the Civil Defence Emergency Management Act 2002, took effect at 3.30pm today and ends on 1 August unless it is extended or ends before then. Mayor Taylor extended her thanks to all the agencies, community groups and volunteers who had supported the Marlborough Emergency Management response and made special note of the advance warning given by Council's hydrology team of the potential impacts of the weather event. Marlborough Emergency Management Group Manager and duty controller Matt Kerr said he had recommended the transition period due to record groundwater levels still affecting the region following the recent weather event and with impacts across the region still 'dynamic and emerging.' 'There is still a risk of ongoing impacts and consequences which may require us to manage, coordinate or direct recovery activities so this transition period is important to facilitate a timely and effective recovery from this event,' Mr Kerr said. Group Recovery Manager Dean Heiford will now assume responsibility for the local transition period.