Stony Plain Road, 124th Street intersection set to re-open after 6 weeks

Stony Plain Road, 124th Street intersection set to re-open after 6 weeks

CBC08-06-2025
Social Sharing
The intersection of Stony Plain Road and 124th Street in Edmonton is expected to re-open to traffic and pedestrians next week, as crews wrap up construction on that section of the Valley Line West LRT, the City of Edmonton and Marigold Infrastructure Projects announced Friday.
The intersection shut down completely on April 21 to allow crews to accelerate work on the LRT line.
"We were going to be in this zone in a heavy way for about a year-and-a-half, and we've condensed that into seven weeks," Jonathan Cox, construction manager with Marigold Infrastructure Projects, the company building the line, said during a media availability Friday.
Cox added that the intersection should open a few days earlier than originally scheduled.
"It is huge," he said. "It's just because of the change of the rules about how we can access and which lanes we keep open."
Brian Latte, the city's director of the Valley Line West, said the progress reflects well on the contractor.
"We're really optimistic that they're just going to continue this effective work through the balance of this year until the end of the project," Latte said at the media availability.
The Valley Line West LRT is now about 40 per cent complete, Cox said.
It is expected to open in 2028.
Businesses frustrated
For six weeks, businesses on the corner of Stony Plain and 124th Street could only be accessed by the sidewalk.
Some businesses nearby the closed-off area also felt the impact, including the Vetrina Cafe, which opened just south of Stony Plain Road last fall.
"It was good. It was many customers," owner Fikra Moese told CBC News Friday. "Now it's very low … because of construction."
Gallery and shop owners have noticed the impact, including the owner of the Lando Gallery, Brent Luebke, who says the signage is insufficient for pedestrians and motorists.
"When people do come to the area, they just don't know where to go," Luebke told CBC News Friday.
From his gallery, he said he has seen a lot of vehicles doing U-turns when they meet the fenced-off area to the north, and pedestrians are equally as lost.
Luebke said he wants the city to put up signs farther down the street to give people more advanced notice.
More construction
Other intersections along the Valley Line West route are still under construction, including the 156th Street interchange and 159th Street/Meadowlark at 89th Avenue, which are set to remain closed until mid-July, the city said.
The subsequent phase of work will start next week, moving up the road to 139th Street and Stony Plain Road in a previously unplanned closure for nine weeks.
Starting June 10, the intersection at 142nd Street and Stony Plain Road will also be partially closed for nine weeks, the city said.
The decision to simultaneously close both intersections will reduce long-term disruption to the neighbourhood, businesses and commuters, the city said in a news release Friday.
'The new normal'
Latte, of the City of Edmonton, said municipal officials are discussing a similar approach on other projects that would see roads and intersections completely closed to speed up work.
"If there's something that we can do at a location that's similar, that has the same results, absolutely it's something we would consider," Latte said.
Cox acknowledged that there may have been some skeptics because of previous city projects that were delayed.
The Valley Line Southeast LRT, for example, was nearly three years behind schedule when it opened in November 2023. The Walterdale Bridge replacement was two years behind when it opened in September 2017.
But Cox described the accelerated approach as "the new normal."
"We can deliver in these time frames," he said.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

$177K fine after flying rock from mine blast in northern Ont. breaks car windshield, injures passenger
$177K fine after flying rock from mine blast in northern Ont. breaks car windshield, injures passenger

CTV News

timean hour ago

  • CTV News

$177K fine after flying rock from mine blast in northern Ont. breaks car windshield, injures passenger

The incident took place in May 2021 at the Magino Gold Project site, a gold mine on Goudreau Road in the Finan Unorganized Township in the District of Algoma. Alamos Gold Inc. and some contractors have been fined a combined $177,500 in connection with a stray piece of rock from a blast that hit a passing vehicle, injuring a passenger. The incident took place in May 2021 at the Magino Gold Project site, a gold mine on Goudreau Road in the Finan Unorganized Township in the District of Algoma. Argonaut Gold's Magino Project in northern Ontario Argonaut Gold's Magino Project in northern Ontario. (Supplied) At the time, the mine was owned by Prodigy Gold, a subsidiary of Argonaut Gold, which amalgamated with Alomos in January of this year. 'At the time, Prodigy Gold was redeveloping the Magino Mine using open pit mining methods to extract leftover gold deposits,' the Ministry of Environment, Conservation and Parks said in a news release. Road wasn't guarded Sigfusson Northern Ltd., a subcontractor, hired a company, Fraser Drill Blast, which detonated a blast May 14, 2021. 'At the time of the blast, a portion of Goudreau Road was not guarded,' the release said. 'As a result of the blast, a piece of fly rock struck a vehicle travelling on the road. The fly rock broke through the windshield of the vehicle and struck the passenger, resulting in a left forearm fracture.' An investigation revealed that the blast location had not been properly plotted. Alamos was fined $67,500, plus a victim surcharge of $16,875. Fraser Drill Blast Management was fined $50,000 plus a victim surcharge of $12,500. Sigfusson Northern Ltd. was fined $60,000, plus a victim surcharge of $15,000. Read the full release here.

Hydro in planning stages of $6.8 billion bipole project
Hydro in planning stages of $6.8 billion bipole project

CTV News

time3 hours ago

  • CTV News

Hydro in planning stages of $6.8 billion bipole project

CTV's Jeff Keele takes a closer look at a planned Manitoba Hydro overhaul of two major transmission projects. Loading the player instance is taking more time than usual Loading the player instance is taking more time than usual Manitoba Hydro is moving ahead with billions of dollars worth of upgrades for two of the province's major transmission lines. The crown corporation said it needs to replace equipment at the converter stations for the Bipole One and Bipole Two transmission lines, which were built in the 1970s and 80s. Hydro media relations officer Peter Chura said 70 per cent of all electricity generated flows from the north to customers in rest of the province. 'It's very important that we maintain the reliability of the system, by replacing aging infrastructure in that system,' said Chura. The project is in the planning phase with a timeline stretching to 2037, according to a rate application document filed by Manitoba Hydro to the Public Utilities Board (PUB). The current cost estimate is $6.8 billion, but Hydro said that figure could change based on the scope, timing and market conditions. 'It's possible the price could go up, the price could go down, the price could change, but we're doing that work right now to establish those facts,' said Chura. Hydro is currently asking the PUB to approve a 3.5 per cent annual rate increases for the next three years for its operations. A long-term projection forecasts the same amounts. Chris Klassen, from the Public Interest Law Centre which represents not-for-profit groups, said Manitoba Hydro needs to prove why this project is so crucial at this time. 'In the upcoming rate hearing, based on Hydro's history, we'll be asking whether Manitoba Hydro's cost estimates are accurate and whether this expensive project is truly needed now,' said Klassen. That history includes the Bipole Three line and the Keeyask Generating Station, that went $3.7 billion over budget. Premier Wab Kinew defended the costly upgrades, saying this is about building Manitoba's future. 'This is exactly the leverage Manitoba has as a low carbon energy power,' said Kinew.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store