Queenswood substation goes ‘up in smoke' yet again

Queenswood substation goes ‘up in smoke' yet again

The Citizen20 hours ago

Queenswood substation goes 'up in smoke' yet again
On the cold winter evening of June 25, a loud explosion rocked Dunstan Road in Queenswood.
For many residents, it was all too familiar: the same power substation that had failed repeatedly in recent months had once again gone 'up in smoke'.
With it, power was lost to large parts of the community for yet another indefinite period.
This substation, which serves key areas in Queenswood, has become notorious for its instability, leaving residents and businesses frequently in the dark.
While initial reports suggest the power trip may have been easily resolved, help never came because of the metro's policy on overtime.
'It is terrifying. The power is now thankfully back on. Sounds to me like the switch just tripped, but thanks to the city council's 'no overtime' policy, no one could go out last night and flip the switch back on,' said resident Theana Olwagen.
Residents have grown increasingly vocal, reporting ongoing power outages that go beyond ordinary inconvenience.
In a statement sent to local officials, Olwagen outlined the depth of the crisis.
'As paying residents, we have consistently observed a lack of action from the city regarding these persistent outages. While power outages have regrettably become common in South Africa, many residents have invested considerable resources to make their homes as comfortable as possible, despite the circumstances. This is particularly frustrating considering our compliance with municipal rates, taxes, and other fees, as well as the fact that rates will be going up from July 1.'
In the last four months alone, Queenswood has endured power disruptions lasting up to 14 days at a time. One resident is keeping an Excel sheet noting complaints lodged on WhatsApp groups in the area.
Most recently, an outage that began on June 20 was briefly resolved on June 22, only to fail again hours later after a brand-new cable was installed at the same location.
Olwagen points to a deeper problem: the metro's fault-reporting and maintenance systems are failing.
'I suspect that the city's reporting system is currently facing challenges with closing tickets related to repairs, whether they have been completed or not. Consequently, we are unable to report this new issue, and we have learned that the depot was unaware of the recurring cable malfunction.'
Residents fear the system may be intentionally closing unresolved cases to create a false sense of progress.
Worse still, they fear follow-up practices have eroded into what many describe as what they see as only attempts to contact residents that do not translate into action.
'Historically, when a ticket was logged, officials from the metro would typically follow up within a day or two. Now, they seem to call, let the phone ring once, and then disconnect before the call can be answered.
'This approach enables the metro's logs to reflect an attempted call without providing any actual follow-up,' confirmed Olwagen.
As of June 26, Webb Road has been without power for four consecutive days. However, this outage is not listed on any official metro communication channels or outage reports.
'It appears that the metro depot may be unaware that the same issue has reoccurred,' Olwagen noted. 'Our specific area has not been mentioned in any of the situation reports on the metro WhatsApp channel. In fact, our ward councillor confirmed that the depot was unaware of Webb Road's current outage.'
The damage goes beyond merely being in the dark.
Residents are facing measurable harm. Essential medical equipment, including oxygen machines, is at risk in power-dependent facilities.
Huis Herfsblaar, a senior care home, is reportedly spending hundreds of thousands per month on diesel to keep generators running. Appliances are damaged by power surges. Students are studying under poor lighting conditions. Food is spoiling in fridges and freezers during long outages.
'These issues are numerous and frustrating, especially considering that we contribute to the resolution of these problems through our rates and taxes,' said Olwagen. 'While some households have opted for solar panels or generators, it's important to recognise that these solutions are not accessible to everyone.'
The community is calling on the metro to urgently respond to enquiries, such as the following questions: What is the exact cause of recurring cable faults along Webb Road, especially given that a brand-new cable failed within hours on June 22? Are repair tickets being prematurely marked as resolved without verification?
The metro's reports confirm the residents' complaints. A progress report from the Prince's Park Depot dated June 24, 09:00, listed:
– 2 medium-voltage area outages – both unresolved;
– 7 low-voltage block outages, including one in Queenswood (Fontana/Kirkby) marked as 'unknown cause' and 'team to investigate';
– 50 single complaints.
This lack of recognition of their troubles and complaints is deeply worrying to residents.
As per internal communications, reference numbers are supposedly escalated every four hours and addressed within 96 hours per the metro's new norms and standards.
That is not happening in practice, according to residents.
Among these residents, there is rising talk of boycotting municipal fees and even legal action, with some consulting with lawyers and power supply specialists.
'I urge that immediate action be taken to address these grievances,' said Olwagen. 'If residents' frustrations boil over, it could lead to a protest that may have considerable, and entirely avoidable, consequences.'
After a utilities oversight meeting of the metro on June 20, DA Councillor Anru Meyer confirmed to Rekord that systemic issues within the energy and water departments are finally being acknowledged at senior levels.
'The 132kV cable infrastructure is failing. Each load point between substations adds new weak points and destabilises the entire network. We are pushing for a complete replacement and upgrade.'
According to Meyer, a group of residents is in discussions with private-sector electrical engineers to assess what a full network upgrade would cost.
His proposal is to recommission a dormant substation within Queenswood, which could offload pressure from the Blesbok substation and the industrial zone nearby.
A petition is being prepared to speed up the implementation of these plans, with the goal of having finance and groundwork in place by the end of the year.
Questions were put to the metro on the outages and residents' complaints, but no response was received by publication.
Do you have more information about the story?
Please send us an email to bennittb@rekord.co.za or phone us on 083 625 4114.
For free breaking and community news, visit Rekord's websites: Rekord East
For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok.
At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Eskom to implement 12-hour power outage in Gauteng on Tuesday
Eskom to implement 12-hour power outage in Gauteng on Tuesday

The South African

time8 hours ago

  • The South African

Eskom to implement 12-hour power outage in Gauteng on Tuesday

Due to planned maintenance, Eskom has scheduled a 12-hour power outage in the Gauteng region. The maintenance is scheduled for Tuesday, 1 July, from 8:00 to 20:00. Eskom said there will be an electricity supply disruption in Aston Lake, Benoni, due to maintenance that will be conducted on the distribution network. 'The power outage will affect customers in Aston Lake on Tuesday, 1 July, from 8:00 – 20:00. The interruption of electricity is necessary to perform essential maintenance on our distribution power lines,' the power utility said. 'Eskom in Gauteng conducts planned maintenance on the distribution electricity network across the province as part of its maintenance plan. It is essential for maintenance to be conducted to service the infrastructure to ensure the safety, reliability, and efficiency of the electricity supply,' Eskom added. In the interest of safety, Eskom said customers should treat all electrical appliances as live at all times during the power outage. Additionally, the power utility said should circumstances beyond its control arise, the planned electricity maintenance in Benoni may not proceed as communicated. Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1. Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X, and Bluesky for the latest news.

Queenswood substation goes ‘up in smoke' yet again
Queenswood substation goes ‘up in smoke' yet again

The Citizen

time20 hours ago

  • The Citizen

Queenswood substation goes ‘up in smoke' yet again

Queenswood substation goes 'up in smoke' yet again On the cold winter evening of June 25, a loud explosion rocked Dunstan Road in Queenswood. For many residents, it was all too familiar: the same power substation that had failed repeatedly in recent months had once again gone 'up in smoke'. With it, power was lost to large parts of the community for yet another indefinite period. This substation, which serves key areas in Queenswood, has become notorious for its instability, leaving residents and businesses frequently in the dark. While initial reports suggest the power trip may have been easily resolved, help never came because of the metro's policy on overtime. 'It is terrifying. The power is now thankfully back on. Sounds to me like the switch just tripped, but thanks to the city council's 'no overtime' policy, no one could go out last night and flip the switch back on,' said resident Theana Olwagen. Residents have grown increasingly vocal, reporting ongoing power outages that go beyond ordinary inconvenience. In a statement sent to local officials, Olwagen outlined the depth of the crisis. 'As paying residents, we have consistently observed a lack of action from the city regarding these persistent outages. While power outages have regrettably become common in South Africa, many residents have invested considerable resources to make their homes as comfortable as possible, despite the circumstances. This is particularly frustrating considering our compliance with municipal rates, taxes, and other fees, as well as the fact that rates will be going up from July 1.' In the last four months alone, Queenswood has endured power disruptions lasting up to 14 days at a time. One resident is keeping an Excel sheet noting complaints lodged on WhatsApp groups in the area. Most recently, an outage that began on June 20 was briefly resolved on June 22, only to fail again hours later after a brand-new cable was installed at the same location. Olwagen points to a deeper problem: the metro's fault-reporting and maintenance systems are failing. 'I suspect that the city's reporting system is currently facing challenges with closing tickets related to repairs, whether they have been completed or not. Consequently, we are unable to report this new issue, and we have learned that the depot was unaware of the recurring cable malfunction.' Residents fear the system may be intentionally closing unresolved cases to create a false sense of progress. Worse still, they fear follow-up practices have eroded into what many describe as what they see as only attempts to contact residents that do not translate into action. 'Historically, when a ticket was logged, officials from the metro would typically follow up within a day or two. Now, they seem to call, let the phone ring once, and then disconnect before the call can be answered. 'This approach enables the metro's logs to reflect an attempted call without providing any actual follow-up,' confirmed Olwagen. As of June 26, Webb Road has been without power for four consecutive days. However, this outage is not listed on any official metro communication channels or outage reports. 'It appears that the metro depot may be unaware that the same issue has reoccurred,' Olwagen noted. 'Our specific area has not been mentioned in any of the situation reports on the metro WhatsApp channel. In fact, our ward councillor confirmed that the depot was unaware of Webb Road's current outage.' The damage goes beyond merely being in the dark. Residents are facing measurable harm. Essential medical equipment, including oxygen machines, is at risk in power-dependent facilities. Huis Herfsblaar, a senior care home, is reportedly spending hundreds of thousands per month on diesel to keep generators running. Appliances are damaged by power surges. Students are studying under poor lighting conditions. Food is spoiling in fridges and freezers during long outages. 'These issues are numerous and frustrating, especially considering that we contribute to the resolution of these problems through our rates and taxes,' said Olwagen. 'While some households have opted for solar panels or generators, it's important to recognise that these solutions are not accessible to everyone.' The community is calling on the metro to urgently respond to enquiries, such as the following questions: What is the exact cause of recurring cable faults along Webb Road, especially given that a brand-new cable failed within hours on June 22? Are repair tickets being prematurely marked as resolved without verification? The metro's reports confirm the residents' complaints. A progress report from the Prince's Park Depot dated June 24, 09:00, listed: – 2 medium-voltage area outages – both unresolved; – 7 low-voltage block outages, including one in Queenswood (Fontana/Kirkby) marked as 'unknown cause' and 'team to investigate'; – 50 single complaints. This lack of recognition of their troubles and complaints is deeply worrying to residents. As per internal communications, reference numbers are supposedly escalated every four hours and addressed within 96 hours per the metro's new norms and standards. That is not happening in practice, according to residents. Among these residents, there is rising talk of boycotting municipal fees and even legal action, with some consulting with lawyers and power supply specialists. 'I urge that immediate action be taken to address these grievances,' said Olwagen. 'If residents' frustrations boil over, it could lead to a protest that may have considerable, and entirely avoidable, consequences.' After a utilities oversight meeting of the metro on June 20, DA Councillor Anru Meyer confirmed to Rekord that systemic issues within the energy and water departments are finally being acknowledged at senior levels. 'The 132kV cable infrastructure is failing. Each load point between substations adds new weak points and destabilises the entire network. We are pushing for a complete replacement and upgrade.' According to Meyer, a group of residents is in discussions with private-sector electrical engineers to assess what a full network upgrade would cost. His proposal is to recommission a dormant substation within Queenswood, which could offload pressure from the Blesbok substation and the industrial zone nearby. A petition is being prepared to speed up the implementation of these plans, with the goal of having finance and groundwork in place by the end of the year. Questions were put to the metro on the outages and residents' complaints, but no response was received by publication. Do you have more information about the story? Please send us an email to bennittb@ or phone us on 083 625 4114. For free breaking and community news, visit Rekord's websites: Rekord East For more news and interesting articles, like Rekord on Facebook, follow us on Twitter or Instagram or TikTok. At Caxton, we employ humans to generate daily fresh news, not AI intervention. Happy reading!

School calendar: June-July holidays start TODAY
School calendar: June-July holidays start TODAY

The South African

timea day ago

  • The South African

School calendar: June-July holidays start TODAY

The good news – is it (?) – for parents is that there's no need to drop off children at school for the next three weeks. It does of course mean finding ways to entertain them after schools around the country broke up for their June-July holidays on Friday, 27 June. The Department of Basic Education (DBE) has confirmed that pupils will return to their desks on Tuesday, 22 July for Term 3. That means a June-July holiday period of 24 days in total, comprising three full weeks plus one extra day – and weekends. The 2025 school year is divided into four terms: Term 1: 15 January to 28 March 15 January to 28 March Term 2: 8 April to 27 June 8 April to 27 June Term 3: 22 July to 3 October 22 July to 3 October Term 4: 13 October to 10 December Prior to 2024, there was a difference in the term dates for inland and coastal schools. In 2024 that changed to a calendar that was identical for all provinces. This remains the case in 2025. The 2025 academic year will consist of 200 school days. Terms 1 and 2 will have 52 days, Term 3 will be the longest at 53 days, while Term 4 will be the shortest with just 43 days. Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1 Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X and Bluesky for the latest news.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store