SIBU (April 25): The upgrading project of the Salim Water Treatment Plant in Sibu has reached 17.96 per cent completion, ahead of the initial target of 6.45 per cent, said Sarawak Minister of Utility and Telecommunication, Dato Sri Julaihi Narawi.
He said the upgrade will double the plant's capacity from 150 million litres per day (MLD) to 300 MLD, enabling a 30 per cent water reserve margin for Sibu and its surrounding areas once completed.
'We've seen steady progress since the project started in May 2024.
'This project is not only progressing smoothly but is also ahead of schedule. We expect it to be completed as planned and capable of supplying clean water to 350,000 residents in the Sibu area,' he told reporters after a working visit to the site at Muka Sauk, Sibu Water Board (SWB), Jalan Stabau today.
Julaihi said the RM291 million project, funded entirely by the Sarawak government, carries a contract value of RM269 million.
It is part of the Sarawak Water Supply Master Plan and supports the implementation of the state's water grid system aimed at interconnecting water treatment plants across the state.
At present, Julaihi said Sibu is served by two main plants — Salim (150 MLD) and Bukit Lima (45 MLD) — with a combined capacity of 195 MLD.
However, daily demand has already surpassed this, reaching 200 MLD, resulting in both plants operating beyond capacity.
'As a long-term solution, the Sarawak government has also approved RM1.1 billion for the replacement and upgrade of old pipes across the state, covering 2,740 km of pipelines, to be implemented over five years.
'For the Sibu Division alone, RM170 million has been allocated,' he said.
He also noted that a new water supply system at Sungai Sadit has been completed and will help boost Sibu's water reserve margin.
'This isn't an overnight solution. It's a long-term plan we're executing through the water master plan and the Sarawak water grid system,' said the Sebuyau assemblyman.
Meanwhile, SWB clarified that the total project cost of RM291.4 million includes construction, land acquisition for the raw water pipeline, site supervision, and professional fees.
Key components of the project include the Phase 2 upgrade of the raw water intake from 150 MLD to 300 MLD; construction of an 8 km new raw water pipeline using 1.4m diameter mild steel pipes; upgrading of the Salim Treatment Plant from 150 MLD to 300 MLD; modification of existing components in Salim Treatment Plant Phases 1 and 2 (sludge bridge, generator set, filters); and construction of a 4km treated water pipeline (2km with 1.6m diameter and 2km with 1.2m diameter).
'The project was awarded to contractor Perbena Emas Sdn Bhd through an open tender and granted on April 18, 2024, with a contract value of RM269,099,341.13.
'Construction works began on May 20, 2024, and are expected to be completed by June 25, 2027,' the board stated.
Upon completion, the upgraded plant will be capable of meeting the water supply needs of 350,000 residents in Sibu, Kanowit, Selangau, Maradong, and Rassau through to 2036.
Accompanying Julaihi during the site visit were the Permanent Secretary of the State Ministry of Utility and Telecommunication, Datu Jafri Lias; Rural Water Supply Department (JBALB) director, Ir Ts Awg Mohammad Fadillah Awg Redzuan; and SWB general manager Abdul Malik Abdullah. julaihi narawi Salim Water Treatment Plant Sibu
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Call to give rural S'wak school-leavers a chance at Universiti Teknologi Petronas
Call to give rural S'wak school-leavers a chance at Universiti Teknologi Petronas

Borneo Post

timea day ago

  • Borneo Post

Call to give rural S'wak school-leavers a chance at Universiti Teknologi Petronas

Julaihi delivers his speech. — Photo by Chimon Upon SEBUYAU (July 27): Malaysia LNG Sdn Bhd (MLNG), a subsidiary of Petronas, has been encouraged to facilitate higher education opportunities at Universiti Teknologi Petronas (UTP) for rural school-leavers, particularly from SMK Sebuyau, to help nurture local talent and bridge the rural-urban education gap. Sarawak Minister of Utility and Telecommunications, Dato Sri Julaihi Narawi, who is also Sebuyau assemblyman, said many rural youths possessed the potential and talent to excel if given access to quality education in a supportive learning environment. 'I strongly hope that Petronas will give special consideration to SPM school leavers here by opening the door for them to pursue their studies at UTP soon,' he told a press conference after officiating the Petronas Powering Knowledge: MLNG Bestari Outreach Programme handing over ceremony at SMK Sebuyau yesterday. He emphasised that such opportunities would allow rural students to experience the same educational environment and facilities as their urban counterparts, offering them a fair platform to succeed. 'They just need the space and support. I believe they can succeed and attain excellent results,' he said. Julaihi said with access to higher education, Sarawak could nurture more local engineering talent to serve in Petronas, the state government, or other players in the oil and gas sector including Petroleum Sarawak Berhad (Petros). 'Therefore, I hope Petronas will respond positively and look into expanding higher education access for rural youth in Sarawak.' Meanwhile, he expressed appreciation for Petronas's contribution through its subsidiary, MLNG, to SMK Sebuyau, particularly in upgrading the school's facilities. He said SMK Sebuyau remains one of the older schools in the area and is in urgent need of a complete replacement. 'I've contributed canopies for the school's use, but they're still insufficient given the growing number of students,' he said, adding that assistance was also channelled under the Rural Transformation Programme (RTP) to construct a new community hall. Julaihi revealed that the current student population at SMK Sebuyau has reached 936. 'With such a large number, I'm truly grateful for Petronas MLNG's support. 'Without facility limitations, this school could probably accommodate even more students,' he said. Julaihi Narawi mlng school-leavers Universiti Teknologi Petronas

SMK Sebuyau gets RM800,000 boost from Petronas under MLNG Bestari programme
SMK Sebuyau gets RM800,000 boost from Petronas under MLNG Bestari programme

Borneo Post

time2 days ago

  • Borneo Post

SMK Sebuyau gets RM800,000 boost from Petronas under MLNG Bestari programme

Julaihi (third right), Abang Yusuf (fourth right), state Education Department officers and others visit the new male dormitory at SMK Sebuyau. – Photo by Chimon Upon SEBUYAU (July 26): SMK Sebuyau received a significant boost of RM800,000 from Petronas, through its subsidiary Malaysia LNG Sdn Bhd, to upgrade its facilities. The contribution was made under the Petronas Powering Knowledge: MLNG Bestari Outreach programme and facilitated the refurbishment of the school's computer lab, Form 5 classroom block and the construction of a new male dormitory. According to Petronas LNG Assets senior vice president Abang Yusuf Abang Puteh, the initiative was not just a Corporate Social Responsibility effort, but a show of their unwavering commitment to rural community development and empowerment. 'We see this effort as a holistic approach that underscores the importance of access to quality education. Education is not only a fundamental right, it is a catalyst for societal progress and transformation,' he said during a handing over ceremony today. The ceremony was officiated by Sarawak Minister of Utility and Telecommunication, Dato Sri Julaihi Narawi. Abang Yusuf said with such support, schools that faced any sort of constraints could now enjoy better facilities and learning resources. 'This initiative acts as a bridge connecting educational institutions, government agencies, the private sector and local communities to build a more sustainable and inclusive learning ecosystem. 'The impact goes beyond academic achievement and contributes to the overall well-being of the community,' he said. The MLNG Bestari Outreach programme has also been extended to other areas including Ulu Roban, Tatau, Sebauh, Betong and Dalat mainly through the provision of learning equipment. Abang Yusuf said that additionally, under the MLNG Borneo Bestari Programme, MLNG was collaborating with Yayasan Sarawak to sponsor 80 Sarawakian students from Form 1 to Form 5 annually to attend residential schools in Peninsula and Sarawak from 2024-2029. 'Our hope is that these sponsored students will excel in their SPM (Sijil Pelajaran Malaysia) exams and become eligible for the Petronas Education Sponsorship Programme, which allows them to further their studies locally and abroad, and ultimately prepare them for employment at Petronas. 'This is our long-term goal — we want to not only support sustainable education but also meet future workforce needs in the oil and gas industry. 'In this regard, I hope that students from Sebuyau will also be among those selected to join the MLNG Borneo Bestari programme as we are confident that children from Sarawak, especially those from rural areas, can keep pace with their peers from major urban centres,' he said. MLNG Bestari Outreach programme Petronas SMK Sebuyau

Abg Jo is Sarawak's ‘Father of Infrastructure Transformation', says Uggah
Abg Jo is Sarawak's ‘Father of Infrastructure Transformation', says Uggah

Borneo Post

time4 days ago

  • Borneo Post

Abg Jo is Sarawak's ‘Father of Infrastructure Transformation', says Uggah

(From front sixth left) Uggah and Abang Johari are seen at the official opening of Tun Taib Mahmud Bridge with other dignitaries. — Ukas photo BINTULU (July 24): Premier Datuk Patinggi Tan Sri Abang Johari Tun Openg has been called the architect of Sarawak's infrastructure transformation. Deputy Premier Datuk Amar Douglas Uggah Embas said Abang Johari's visionary leadership and financial acumen have enabled major developments across the state. 'I believe the Premier rightfully deserves the title as the 'Father of Infrastructure Transformation' in Sarawak,' Uggah said during the official opening of Tun Taib Mahmud Bridge here last night. Uggah described Abang Johari as a leader with the people at heart, who is determined to ensure that roads and bridges across Sarawak are built swiftly to spur socioeconomic growth. 'He is incredibly resourceful. Without him, I don't know where we would have gotten the funds. 'Last year alone, Sarawak recorded RM14.2 billion in income, compared to just RM6.8 billion in 2017,' he said, noting that more progress can be expected due to the Premier's strategic planning. He pointed out the Sarawak Public Works Department (JKR) has been entrusted to implement infrastructure projects worth RM42.6 billion, all financed by the state's own funds. He noted that under the state's ongoing bridge-building programme, five bridges are completed and six more expected to be finished by 2026, including the iconic Batang Lupar 1 Bridge, which at 4.8km will be the longest in Sarawak. 'We're aiming for its completion by March 2026, but we will try our best to get it done by December 2025,' he said. On the Marina Bridge in Miri, he said it may also be completed earlier than expected, with the contractor indicating they could finish the four-year project in just three. 'By June 2026, you'll be able to drive from Kuching to Miri without relying on a ferry, a direct result of the Premier's bridge development agenda,' Uggah said. He emphasised that no other state in Malaysia is undertaking a bridge construction effort as extensive as Sarawak's with 17 major bridges currently planned or underway. 'Just now, (Minister Of Food Industry, Commodity and Regional Development) Dato Sri Dr Stephen Rundi mentioned additional bridges in Bintulu, and I heard that the Premier has approved more in Sibu and Sebuyau, which could bring the total to 20 bridges,' he said. Focusing on Bintulu, Uggah said RM1.1 billion worth of infrastructure projects are being rolled out, including the RM117.9 million new administrative centre and an RM80 million dual carriageway road from Tun Taib Mahmud Bridge to Bintulu Airport worth. 'All of these projects are fully financed by the Sarawak government. The opposition used to dismiss them as mere talk, but now they're seeing real, physical results, not just rhetoric, but proof on the ground. 'GPS doesn't just make promises, we fulfil them. That's the commitment of the GPS government under Premier Abang Johari,' he added.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store