MMRCL releases metro contractors' dues amid property tax wrangle
Four private contractors—Dogus Soma JV, CEC-ITD JV, L&T STEC JV and HCC, had approached the Bombay high court, challenging the BMC's property tax demands under Section 184 of the Railways Act, 1989, which exempts railway land from such levies. They argued that the casting yard at Wadala Truck Terminal, used for Metro construction, falls under this exemption.
On March 18, Hindustan Times was the first to report that MMRCL had warned contractors that payments would be withheld unless they cleared their property tax dues with the BMC. The contractors had, in March last year, filed writ petitions, prompting the high court to restrain the BMC from taking coercive action through an interim order issued on April 30, 2024. This relief has since been extended.
In a letter dated May 14, 2025, the BMC informed its legal department that it stood by its position: casting yards are taxable, and contractors are jointly and severally liable.
Following a hearing on March 27 last year before additional municipal commissioner Ashwini Joshi, a formal order upheld the BMC's claims, and caveats were filed in court to protect its legal standing.
In its letter, of which HT has a copy, the BMC reiterated, 'Given the ongoing judicial proceedings, no fresh notices have been issued or enforcement action taken against the contractors.'
In view of the ongoing legal challenge, MMRCL has now released the contractors' withheld payments after securing an undertaking that links future tax settlement to contractual obligations. MMRCL had also sought a revised tax calculation based on reduced floor space index (FSI), which the BMC provided on January 31, 2025.
Advocate Prerak Choudhary, representing the contractors, said, 'Our case is that the BMC's property tax demands violate Section 184 of the Railways Act, 1989, as no tax is payable on casting yards used for the metro project. We challenged these demands before the Bombay high court, which granted interim relief against coercive recovery. Despite this, the contractors' payments were withheld at the BMC's request, though they are now being released. While the immediate issue is resolved, we await the court's decision on the broader legality of the tax demands.'
The final verdict in the case is still awaited.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Time of India
5 hours ago
- Time of India
‘Illegal' market complex along flight path yet to be razed: Officials
Bhubaneswar: An unauthorised two-storey market complex in Jagamara, which falls along the approach path of flights at Biju Patnaik International Airport, is yet to be demolished despite repeated reminders to the civic authorities, BPIA officials said. Tired of too many ads? go ad free now Tall trees around the area are also posing as obstructions during aircraft landing. Officials said getting a no-objection certificate (NOC) from the airport authorities is mandatory to get approval of Bhubaneswar Municipal Corporation for any construction. But in the case of the complex, no NOC was obtained, they said. "We flagged our concerns several times before the city authorities. They have so far cut three coconut trees. But the two-storey building is completely illegal," said airport director Prasanna Pradhan. He further said the airport is not empowered to serve notice and order demolition as per existing rules, and it is the mandate of Bhubaneswar Municipal Corporation (BMC), Bhubaneswar Development Authority (BDA), and in some cases, the general administration department. "The Centre issued draft rules to regulate and remove obstructions such as buildings and trees that interfere with aircraft. The draft Aircraft (Demolition of Obstructions Caused by Buildings and Trees, etc.) Rules, 2025, were released under the Bharatiya Vayuyan Adhiniyam, 2024. It was in the public domain for 21 days for feedback. It is likely to be passed in Parliament very soon, after which airport authorities will be empowered to remove obstructions. This will reduce the cumbersome process of moving multiple agencies," Pradhan added. Tired of too many ads? go ad free now The Airport Environment Management Committee (AEMC) pointed out the obstructions and safety issues. The BMC commissioner chairs the AEMC meeting. BPIA authorities recently surveyed the area jointly with officials of BMC, BDA, general administration department, and police. "There should not be any infringement on the approach light and obstacle-free zone (OFZ) of the airport," an airport official said. "After cutting the coconut trees, other tall trees along the airport's approach path will be felled," said BMC commissioner Rajesh Patil. "We are taking steps to remove more obstructions. The building owners will also be served a notice," he added. During landing and takeoff, birds flutter from trees as high as to hit an aircraft nose, fuselage, windshield and engine, which can pose potential danger to flights and may end in a crash, airport officials said.


Time of India
12 hours ago
- Time of India
High-level committee to go into accusations of corruption at Mumbai dumping ground
Mumbai: Industries minister Uday Samant on Friday announced a high-level inquiry committee to investigate alleged corruption and irregularities at BMC's Kanjurmarg dumping ground. Samant said action would be taken against the contractor based on the findings of the report, which will be available in 60 days. He mentioned that the govt has instructed the BMC to find an alternative location for a new dumping ground to replace the Kanjurmarg site. Samant was responding to a calling attention motion moved by BJP MLA Mihir Kotecha. Kotecha said that 16 lakh residents of Ghatkopar, Vikhroli, Kanjurmarg, Nahur, Bhandup and Mulund were affected by the strong, foul stench every night because of the Kanjurmarg dumping ground. You Can Also Check: Mumbai AQI | Weather in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai He explained that the entire 6,000 tonnes of waste from Mumbai city is brought to the Kanjurmarg landfill every day for processing. "The contract to process the waste at this landfill was given to M/s Anthony Lara Enviro Solutions Private Ltd for a period of 25 years from 2011 to 2036. As per the terms of the contract, the contractor is responsible for the entire waste processing, maintenance, and stench control. Sixteen lakh residents have been suffering from a strong foul stench every night," Kotecha said. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like You Won't Believe the Price of These Dubai Apartments Binghatti Developers FZE Get Offer Undo Kotecha pointed out that the contractor is required to spend Rs 5 lakh per day to implement zero order management, but the penalty provision is only Rs 50,000. "So, this contractor is saving Rs 330 crore. How will the govt recover it, and will the govt terminate the contract? Will an audit by an independent agency be ordered? What action will be taken against the BMC officials for not following the govt's instructions? Will solid waste management (SWM) department officials be sent to Kannamwarnagar for 15 days to understand the seriousness?" asked Kotecha. "The enquiry committee will include class I officers from each division. A third-party audit will also be conducted. This committee will submit its report within 60 days. Action will be taken against the contractor based on the findings of the committee report. A show-cause notice will be issued to the BMC officials for not following the govt's orders. If a satisfactory response is not received from them, action will be taken against them," Samant said.


Time of India
13 hours ago
- Time of India
Bombay high court directs Mumbai Metro Rail Corporation to reconstruct heritage limestone finial at Petit Institute
1 2 Mumbai: The Bombay high court directed the Mumbai Metro Rail Corporation Ltd (MMRCL) to reconstruct a heritage limestone finial feature of the iconic JN Petit Institute, which fell during the construction of Metro Line III in 2017. A division bench of Justices M S Sonak and Jitendra Jain, in its July 10 judgment, said, "Whilst the march of development and infrastructural projects cannot be halted in a city like Mumbai, such a march cannot be permitted to run roughshod over the concerns of preserving and maintaining heritage buildings for posterity." The high court clarified that its prima facie observations are not intended to prejudice either the trust or the state and MMRCL, and kept all contentions open on either side. The high court was disposing of a petition filed in 2018 by D V M Patel and Homa Petit, trustees of the JN Petit Institute, a Grade II-A heritage structure located at DN Road in Fort. You Can Also Check: Mumbai AQI | Weather in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai Construction of the underground metro line was completed in 2023, said the high court. It said the petitioners retain the liberty to initiate legal proceedings in case any damage arises when the metro becomes operational. The high court said that regarding the fallen finial it had "no serious doubts about the connection to MMRCL's Metro Line III project works". by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Gentle Japanese hair growth method for men and women's scalp Hair's Rich Learn More Undo The judgment noted that records showed it "collapsed on 25 Aug 2017, when the petitioners were constantly complaining about the vibrations and the failure to monitor them". The trust filed a petition in 2017, and following a stay of work by the high court on Sept 15, 2017, in front of the institute, the court appointed an expert committee which recommended precautionary measures. Only then did the HC, on 29 November 2017, vacate the restraint and allow MMRCL to resume work. The HC on Thursday noted that "fortunately, the MMRCL, without prejudice to its rights and contentions and without accepting any liability, has now agreed to reconstruct the limestone finial …". The high court termed as "too speculative" the petitioning trustees' concern "at this stage" over damage likely to be caused once the underground metro becomes operative and said the averments of MMRCL in its affidavit address some of the trust's concerns. The high court observed that MMRCL's statements suggest that the alignment of the metro tunnel is not directly under the Petit building. "The tracks run approximately four to five metres away horizontally and around 25 metres below ground level," the high court said in its judgment, recording MMRCL's claims that noise levels are within legal norms and even the maximum recorded vibration value of 55 VdB at surface ground level is lower than the permitted limit of 72 VdB. "At this point, it is not for us to either accept or reject the above statements," the high court said. The high court directed MMRCL "to reconstruct/restore/replicate the limestone finial previously forming a part of the building at its own costs" subject to various conditions including full cooperation of the trust. The trust must obtain all prior requisite permissions from authorities, said the high court, for the restoration work. The court said work must finish within eight months of the last permission once received. The trust operates the JN Petit Reading Room and Library since 1856. The plea concerned JN Petit Institute, along with an arcade constructed on the land in Fort, south Mumbai, a neo-gothic revival style building dating back to 1898. It houses a lakh books and was renovated in 2014-15 and was conferred the UNESCO Award of Distinction for Cultural Heritage Conservation. The building features various ornamental, decorative, and distinctive elements, including a circular staircase tower, bouquets, finials, and tower turrets that shape its silhouette. The building's foundation is "only around three metres deep", the trustees said.