Lepelle responds to water project criticism

Lepelle responds to water project criticism

The Citizen10-07-2025
Under fire for slow delivery, Lepelle says its leadership overhaul and new contractors are already showing real progress.
The department of water and sanitation under Minister Pemmy Majodina is partly blaming the Lepelle Northern Water board (LNW) for the slow provision of water and the completion of bulk water infrastructure projects in Limpopo.
Lepelle is a state-owned water utility responsible for bulk water provision and the construction of bulk water projects in Limpopo on behalf of the national department.
Deputy Minister David Mahlobo said many of the projects being implemented by LNW are subjected to long delays.
Many Lepelle Northern Water board projects delayed for long
In addition, there is widespread dissatisfaction with the performance of LNW among water service authorities in Limpopo.
He said the department has arranged for Rand Water and Lebalelo Water User Association to provide support to LNW to improve its infrastructure procurement and project and contract management.
ALSO READ: 'They will rue the day we crossed paths': Limpopo mayor threatens construction mafia after stalled projects
He said LNW is also getting support from the Government Technical Advisory Service in the National Treasury to improve its infrastructure procurement.
According to Mahlobo, the Infrastructure Fund is now assisting Lepelle with financial structuring and project management for the Olifantspoort-Ebenezer project.
Mahlobo said the department has reduced the allocation of new projects to Lepelle to enable the agency to focus on the completion of its existing projects, while improving its service to water authorities in Limpopo.
Development Bank of South Africa appointed as implementing agent
Mahlobo said the Development Bank of South Africa has been appointed as implementing agent for the Musina-Zimbabwe water transfer scheme and the Nandoni water treatment plant upgrade.
The agency defended itself, saying since the new leadership took office in 2021, LNW has been on a significant turnaround path.
ALSO READ: Limpopo villagers plead with rain queen to end drought
'From early 2023, LNW has instituted several reforms and operational improvements, particularly in the management and execution of capital projects.
'Many of the older, underperforming contractors have been terminated and new capable service providers have been appointed,' said LNW chief executive officer Cornelius Ruiters.
New appointments delivering measurable progress
Ruiters said the new appointments were delivering measurable progress and projects were now being implemented within budget and on schedule, 'a testament to a new culture of professionalism and accountability at LNW'.
'We have also restructured our internal operations, including the establishment of a dedicated engineering division staffed by qualified professionals to oversee all infrastructure projects.'
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Giyani Water Project nears completion as additional R3bn needed
Giyani Water Project nears completion as additional R3bn needed

The Citizen

time5 days ago

  • The Citizen

Giyani Water Project nears completion as additional R3bn needed

Majodina explained that several key components of the Giyani Water Project have already been completed. The Giyani Water Intervention Project requires an additional R3 billion to complete household connections and reticulation to all targeted villages, with the bulk infrastructure component expected to finish by September 2025, Water and Sanitation Minister Pemmy Majodina told parliament. DA MP Farhat Essack had asked the minister when the project would be completed and what additional expenditure was required for its completion. Giyani Water project major components nearly complete Majodina explained that several key components of the multi-faceted water intervention project have already been completed. The Nandoni-Nsami Bulk Pipeline project was 'completed in December 2023 and currently supplies Giyani WTWs with an average of 15Ml/d of raw water.' The 40km raw water pipeline runs from Nandoni Dam in Vhembe District Municipality into a balancing dam at Giyani Water Treatment Works. A parallel 26km treated pipeline, ending at Muswani under Collins Chabane Local Municipality, was also completed in December 2023. According to Majodina, the refurbishment of the Giyani Water Treatment Works to restore original production capacity to 30 megalitres per day was 'completed in June 2024'. ALSO READ: ARVs not found in Gauteng drinking water, says Rand Water Bulk infrastructure nearing final stage The minister revealed that the Giyani Water Services Project, which involves constructing 325km of bulk pipelines from the Giyani Water Treatment Works to include service reservoirs supplying 55 villages in Giyani, is in its final phase. Majodina reported that 'the overall project progress is currently at 90%' with 'project completion anticipated by September 2025'. Village connections progress The household reticulation component shows mixed progress across different phases. Phase 1 covers reticulation and household metered connections to 24 of the 55 villages. According to Majodina, the project was complete in 23 of the 24 villages, with completion of Risinga View Village set for the end of July 2025. Phase 2, covering reticulation and household metered connections to 31 villages, has been divided into two sub-phases. Phase 2a covers 15 villages, while Phase 2b covers 16 villages. The minister indicated that Phase 2 is 'still under planning' with business plans for Phase 2a having been 'provisionally approved pending budget confirmation to be implemented during the 2025-26 financial year.' Phase 2b will commence upon completion of Phase 2a, she added. ALSO READ: Water projects worth R50bn to be constructed in Limpopo while progress on older projects stalls Future upgrades and funding requirements A planned upgrade of the Giyani Water Treatment Works from 30 megalitres per day to 40 megalitres per day, along with the development of well fields, is still in the early stages. The implementing agent is currently 'processing Water Use Licence application with the department, and thereafter the IRS will be approved,' Majodina explained. She noted that funding for this upgrade is already 'included in the RBIG MTEF budget'. R3 billion additional investment needed The minister detailed that the additional R3 billion required breaks down specifically for the remaining reticulation and household connections. The costing covers service reservoirs, pump stations, reticulations and household yard metered connections. Phase 2a, serving 15 villages and 21,403 households, requires R1.5 billion, while Phase 2b, serving 16 villages and 20,972 households, requires an additional R1.5 billion. Majodina emphasised that 'the upgrade of the Giyani WTW does not require additional allocations, as it is already catered for under the MTEF allocations of the department'. READ NEXT: Residents of Limpopo village fed up after not getting water for 15 years

Lepelle responds to water project criticism
Lepelle responds to water project criticism

The Citizen

time10-07-2025

  • The Citizen

Lepelle responds to water project criticism

Under fire for slow delivery, Lepelle says its leadership overhaul and new contractors are already showing real progress. The department of water and sanitation under Minister Pemmy Majodina is partly blaming the Lepelle Northern Water board (LNW) for the slow provision of water and the completion of bulk water infrastructure projects in Limpopo. Lepelle is a state-owned water utility responsible for bulk water provision and the construction of bulk water projects in Limpopo on behalf of the national department. Deputy Minister David Mahlobo said many of the projects being implemented by LNW are subjected to long delays. Many Lepelle Northern Water board projects delayed for long In addition, there is widespread dissatisfaction with the performance of LNW among water service authorities in Limpopo. He said the department has arranged for Rand Water and Lebalelo Water User Association to provide support to LNW to improve its infrastructure procurement and project and contract management. ALSO READ: 'They will rue the day we crossed paths': Limpopo mayor threatens construction mafia after stalled projects He said LNW is also getting support from the Government Technical Advisory Service in the National Treasury to improve its infrastructure procurement. According to Mahlobo, the Infrastructure Fund is now assisting Lepelle with financial structuring and project management for the Olifantspoort-Ebenezer project. Mahlobo said the department has reduced the allocation of new projects to Lepelle to enable the agency to focus on the completion of its existing projects, while improving its service to water authorities in Limpopo. Development Bank of South Africa appointed as implementing agent Mahlobo said the Development Bank of South Africa has been appointed as implementing agent for the Musina-Zimbabwe water transfer scheme and the Nandoni water treatment plant upgrade. The agency defended itself, saying since the new leadership took office in 2021, LNW has been on a significant turnaround path. ALSO READ: Limpopo villagers plead with rain queen to end drought 'From early 2023, LNW has instituted several reforms and operational improvements, particularly in the management and execution of capital projects. 'Many of the older, underperforming contractors have been terminated and new capable service providers have been appointed,' said LNW chief executive officer Cornelius Ruiters. New appointments delivering measurable progress Ruiters said the new appointments were delivering measurable progress and projects were now being implemented within budget and on schedule, 'a testament to a new culture of professionalism and accountability at LNW'. 'We have also restructured our internal operations, including the establishment of a dedicated engineering division staffed by qualified professionals to oversee all infrastructure projects.'

Minister Majodina calls for SADC unity to tackle Africa's R528 billion water investment gap
Minister Majodina calls for SADC unity to tackle Africa's R528 billion water investment gap

IOL News

time07-07-2025

  • IOL News

Minister Majodina calls for SADC unity to tackle Africa's R528 billion water investment gap

Minister of Water and Sanitation, Ms Pemmy Majodina, engages SADC counterparts in Harare to rally support for Africa's R528 billion annual water investment drive. The Minister of Water and Sanitation, Pemmy Majodina, has successfully placed the upcoming Africa Water Investment Summit on the agenda of the Southern African Development Community (SADC) at the 43rd Joint Meeting of Ministers responsible for Energy and Water. The meeting, held in Harare, Zimbabwe, from July 3 to 4, brought together regional leaders to strengthen cooperation on critical water and energy issues. Minister Majodina, who attended the meeting alongside Minister of Electricity and Energy, Kgosientsho Ramokgopa, used the platform to urge SADC ministers to unite behind the upcoming Africa Water Investment Summit, co-hosted by South Africa and the African Union-Continental Africa Water Investment Programme (AU-AIP). The summit will take place in Cape Town from August 13 to 15, 2025, within the context of South Africa's G20 Presidency Africa faces a staggering US$30 billion (approximately R528 billion) annual water investment gap, threatening the continent's economic growth and water security. The upcoming summit aims to mobilise financial commitments to close this gap and advance bankable water and sanitation infrastructure projects across Africa.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store