logo
Dublin's Luas network set for major upgrades and new lines under 2050 plan

Dublin's Luas network set for major upgrades and new lines under 2050 plan

Irish Independent14 hours ago
At a recent Lean Construction Ireland webinar, Anthony Duffy, Head of Project Services at TII, outlined its vision to expand and modernise Dublin's light rail network over the next 25 years.
He said the agency is moving away from piecemeal project delivery towards a more coordinated, system-wide approach.
'We're not simply delivering individual projects,' Mr Duffy said.
'We're building a connected, strategic light rail network that will serve Dublin and its surrounding region right through to 2050.'
The Luas 2050 plan covers everything from new lines in Finglas, Lucan, and Poolbeg, to the complete replacement of the ageing Red Line fleet between 2028 and 2029, designed to ease overcrowding during busy periods.
In addition, upgrades to key depots and interchanges, including the Red Cow Bus Interchange, are intended to streamline connections between bus and tram services and reduce delays.
New stops will also be introduced in developing areas such as City Edge on the Naas Road.
Mr Duffy acknowledged the challenge of bringing multiple projects together under one flexible strategy.
'With the network's technological complexity and the urgent need to update key assets, Luas 2050 is crucial to coordinating efforts and planning for future demand,' he said.
However, the pace of the rollout faces barriers outside the project team's control, including planning delays, requirements set by the National Transport Authority (NTA), and Government procedures.
ADVERTISEMENT
Workshops held by TII identified these issues as key bottlenecks slowing down progress.
A presentation given to the TII Board earlier this year highlights that accelerating the Luas expansion will require cooperation between TII, the NTA, local authorities, and political stakeholders to overcome these hurdles.
The same presentation reveals an ambitious timeline, dependent on funding.
By 2026, TII hopes to be actively working on five Luas lines, including Finglas (aiming to start construction soon after planning permission); Lucan (finalising route selection); Cork (in preliminary design); and Poolbeg (project commencement pending official approval).
A fifth new line, yet to be confirmed, is also being considered as part of the overall plan.
Alongside these projects, major works such as the Red Cow Bus Interchange and depot extension are slated for completion between 2027 and 2028, alongside the awarding of a rolling stock contract and order for the new Red Line fleet.
Looking further ahead, the plan targets commencing a new Luas line every 1-2 years from 2029 onwards to meet the 2050 vision.
While the network's current Green Line is expected to have sufficient capacity until around 2027, the Red Line is already at or near capacity, with constraints on increasing services without more trams and depot expansion.
TII's longer-term vision also includes potential orbital lines around Dublin, designed to improve connectivity between suburbs without needing to travel into the city centre.
However, these remain dependent on Government funding and planning.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Dublin's Luas network set for major upgrades and new lines under 2050 plan
Dublin's Luas network set for major upgrades and new lines under 2050 plan

Irish Independent

time14 hours ago

  • Irish Independent

Dublin's Luas network set for major upgrades and new lines under 2050 plan

At a recent Lean Construction Ireland webinar, Anthony Duffy, Head of Project Services at TII, outlined its vision to expand and modernise Dublin's light rail network over the next 25 years. He said the agency is moving away from piecemeal project delivery towards a more coordinated, system-wide approach. 'We're not simply delivering individual projects,' Mr Duffy said. 'We're building a connected, strategic light rail network that will serve Dublin and its surrounding region right through to 2050.' The Luas 2050 plan covers everything from new lines in Finglas, Lucan, and Poolbeg, to the complete replacement of the ageing Red Line fleet between 2028 and 2029, designed to ease overcrowding during busy periods. In addition, upgrades to key depots and interchanges, including the Red Cow Bus Interchange, are intended to streamline connections between bus and tram services and reduce delays. New stops will also be introduced in developing areas such as City Edge on the Naas Road. Mr Duffy acknowledged the challenge of bringing multiple projects together under one flexible strategy. 'With the network's technological complexity and the urgent need to update key assets, Luas 2050 is crucial to coordinating efforts and planning for future demand,' he said. However, the pace of the rollout faces barriers outside the project team's control, including planning delays, requirements set by the National Transport Authority (NTA), and Government procedures. ADVERTISEMENT Workshops held by TII identified these issues as key bottlenecks slowing down progress. A presentation given to the TII Board earlier this year highlights that accelerating the Luas expansion will require cooperation between TII, the NTA, local authorities, and political stakeholders to overcome these hurdles. The same presentation reveals an ambitious timeline, dependent on funding. By 2026, TII hopes to be actively working on five Luas lines, including Finglas (aiming to start construction soon after planning permission); Lucan (finalising route selection); Cork (in preliminary design); and Poolbeg (project commencement pending official approval). A fifth new line, yet to be confirmed, is also being considered as part of the overall plan. Alongside these projects, major works such as the Red Cow Bus Interchange and depot extension are slated for completion between 2027 and 2028, alongside the awarding of a rolling stock contract and order for the new Red Line fleet. Looking further ahead, the plan targets commencing a new Luas line every 1-2 years from 2029 onwards to meet the 2050 vision. While the network's current Green Line is expected to have sufficient capacity until around 2027, the Red Line is already at or near capacity, with constraints on increasing services without more trams and depot expansion. TII's longer-term vision also includes potential orbital lines around Dublin, designed to improve connectivity between suburbs without needing to travel into the city centre. However, these remain dependent on Government funding and planning.

Plans for new Luas lines 'should be fast-tracked'
Plans for new Luas lines 'should be fast-tracked'

Extra.ie​

time2 days ago

  • Extra.ie​

Plans for new Luas lines 'should be fast-tracked'

An ambitious plan for the future of the Luas would see two new circular lines running on the outskirts of Dublin city centre, along with an orbital route outside the M50 motorway. One of the suggested circular lines would run from Finglas past DCU, through Drumcondra, along Griffith Avenue, and on to Marino and Fairview. The Luas 2050 vision would also include new lines to Blanchardstown, Clondalkin, Balgriffin, and Clongriffin, according to an internal presentation from Transport Infrastructure Ireland (TII). A new Luas line 'should be fast-tracked'. Pic: Getty Images It said light rail would be a key part of future public transport in the capital and plans for new lines should be accelerated. However, it found issues with the existing Luas network and highlighted that there are not enough trams on the Red Line which connects the Docklands to Tallaght and Saggart. It said there are constraints to increasing services and managing future demand, but there may now be an 'appetite to address' some of the challenges, given the success of the Luas network. TII said longer 55-metre trams might not be a solution as they are slower, and so much of the Red Line is shared with cars. Pic: Sam Boal/ It said that this has created possible safety issues, and more trams are needed instead of longer vehicles. The presentation said the capacity of the Green Line, which runs from Broombridge to Sandyford and Bride's Glen is 'OK for [the] short term'. It said some changes and increases in service were possible, and this could be accommodated with the existing fleet of trams. TII said there were issues with depots, with the main facility at Sandyford 'land constrained' and unsuitable for expansion. The presentation said there is room at Broombridge for an increase in size, but this is not ideal 'for operational reasons.' Pic: It said an option around land acquisition and possible expansion at the Red Cow could also be looked at in the future. The slideshow also put forward the possibility of adding lines, including an ambitious plan for circle routes over the next 25 years. It said in the short term, work should continue on an extension to Poolbeg as well as studies on the efficiency and flexibility of the Red and Green Lines. The slideshow suggested a 'new Luas project' should be examined, with one possibility being a connection to UCD. It also recommended moving forward with an extension to Bray with an indicative start date of between 2028 and 2030. The document said workshops on accelerating project delivery would be useful to help speed up development of new projects. The presentation said, from 2029 onwards, they should be starting work on a new Luas line every one to two years to have an advanced network by 2050. A spokesman for TII said: 'Transport Infrastructure Ireland, taking a strategic look ahead to 2050, allows for public and decision-making bodies – such as the Department of Transport and National Transport Authority – to see where potential investments can be made to support the country's future growth and development.'

Finglas apartment plans on proposed Luas route withdrawn following community pushback
Finglas apartment plans on proposed Luas route withdrawn following community pushback

Dublin Live

time2 days ago

  • Dublin Live

Finglas apartment plans on proposed Luas route withdrawn following community pushback

Our community members are treated to special offers, promotions and adverts from us and our partners. You can check out at any time. More info Plans to develop over 600 apartments on a site along the proposed Finglas Luas route have been withdrawn following serious concerns from the local community. The plans for 607 residential units within five blocks were intended for the KSG Group Site on McKee Avenue with heights of up to 10 storeys. The plans were submitted as a singular application despite the Jamestown masterplan for the area. This planning application was submitted for a site that was earmarked in the masterplan for primarily three but up to eight storeys. While a reason for withdrawal was not forthcoming through Dublin City Council planning, the application received considerable pushback from the community. Dozens of observations were submitted on the planning application from locals, resident groups and politicians, primarily objecting to the proposal in its current form. Issues raised included traffic concerns, overdevelopment of the site against the master plan, the need for the Luas and the overcapacity of the local water and sewage network. Fianna Fail councillor Keith Connolly raised concerns surrounding the lack of alignment with the masterplan for the area. He said: "The Masterplan clearly requires that developments be brought forward in a phased, coordinated manner, including the provision of surface water management infrastructure, green space, and community facilities. "This application appears to be a standalone development with no demonstrated coordination with adjacent landowners or a comprehensive Surface Water Management Plan(SWMP). There has been no evidence of a holistic approach to the side or any engagement with surrounding landowners, particularly those on the Jamestown Road side of the masterplan." While his party colleague, TD Paul McAuliffe added: "The Jamestown Masterplan, as adopted by the elected members of Dublin City Council,provides the agreed framework for development in this area. It is essential that all applications adhere to its principles to ensure a sustainable, inclusive, and well-serviced community." While people Before Profit Cllr Conor Reddy said that the proposal "moves further away from the goal of a sustainable, mixed community rather than private rental". One of the adjacent land owners also had concerns about an access road planned for the their site and the lack of access to the proposal site for construction due to no agreement or engagement. They claimed that the applicant created a "ransom strip" with the proposal. Join our Dublin Live breaking news service on WhatsApp. Click this link to receive your daily dose of Dublin Live content. We also treat our community members to special offers, promotions, and adverts from us and our partners. If you don't like our community, you can check out any time you like. If you're curious, you can read our Privacy Notice. For all the latest news from Dublin and surrounding areas visit our homepage.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store