Consumers pay Rs69b for idle plants
The inefficiencies in the country's electricity transmission system have burdened consumers with capacity payments of Rs69 billion in the quarterly tariff adjustment (QTA) for ex-Wapda distribution companies (DISCOs) for the third quarter of financial year 2024-25.
Three power plants had been operating at lower capacity during the period under review, but they received Rs69 billion in capacity payments, which the electricity consumers had to pay.
National Electric Power Regulatory Authority (Nepra) Member (Technical) Rafique Ahmad Shaikh has pointed out inefficiencies in the country's transmission system due to which Rs69 billion was paid to three coal-fired plants in capacity charges despite extremely low utilisation. He submitted these comments in his additional note on the QTA for the third quarter of 2024-25, in which a reduction of Rs1.55 per unit was allowed to refund Rs52.6 billion to the consumers of DSICOs and K-Electric (KE) in the bills for May, June and July 2025.
According to him, transmission constraints continue to limit the utilisation of several cost-effective power plants located in the southern region, notably Port Qasim, China Power and Lucky Electric. Despite their potential to provide affordable electricity, these plants reported extremely low utilisation factors – approximately 1% for Port Qasim, 10% for China Power and 0% for Lucky Electric – during the quarter.
Nevertheless, they claimed substantial capacity payments amounting to Rs26.95 billion, Rs30.88 billion and Rs11.26 billion, respectively. In total, around Rs69.09 billion was claimed in capacity charges despite minimal generation.
This reflects a major inefficiency in the system and underscores the urgent need to address transmission bottlenecks and improve generation dispatch practices to ensure the optimal use of the available low-cost generation resources.
It is noted that the capacity claimed by DISCOs for the third quarter of FY 2024-25 amounted to Rs362.395 billion, which was significantly lower than the reference figure of Rs459.286 billion. During the same period, electricity sales stood at 19,968 gigawatt hours (GWh) compared to reference sales of 21,846 GWh in the corresponding period.
Ordinarily, a decline in electricity sales would result in an upward adjustment in capacity charges due to the fixed-cost nature of capacity payments.
However, during this quarter, the termination of certain power purchase agreements (PPAs) and other adjustments related to the independent power producers (IPPs) operating within the system have contributed to a reduction against the projected capacity payment. Consequently, this led to a negative adjustment in the third quarter of FY 2024-25.
Although the quarterly adjustment for the third quarter decreased significantly, he said that enhanced governance and more efficient system operations could have further improved electricity sales, potentially leading to an even greater reduction in the adjustment amount. In that regard, several key observations were highlighted for consideration and focused action by the relevant stakeholders.
Genco-II (Guddu old), Genco-III (TPS Muzaffargarh) and Genco-I (Jamshoro Power Company) collectively claimed capacity payments of Rs1.237 billion during the quarter – Rs469 million, Rs350 million and Rs418 million respectively – despite generating no electricity during the period.
These plants are characterised by high generation costs and poor operational efficiency, with little-to-no likelihood of receiving dispatch orders from the system operator in the future, given the availability of abundant and more cost-effective surplus capacity in the system. Continuing capacity payments to such non-operational and inefficient assets imposes an unnecessary financial burden on both the power sector and end consumers. A targeted and strategic review is, therefore, essential to rationalise these expenditures and improve the overall sector efficiency.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Express Tribune
10 hours ago
- Express Tribune
Centre to help resolve Sindh's water woes
The federal government assured the Sindh government on Thursday of its full cooperation in addressing the province's water-related issues, including K-IV Phase-1, improvements in the Hub Canal water share, the Right Bank Outfall Drain (RBOD), and water distribution under the 1991 Water Accord. Sindh Chief Minister Syed Murad Ali Shah held a meeting with Federal Water Resources Minister Moin Wattoo at the Chief Minister House to discuss key water projects. The issue of water shortage for Karachi metropolis figured prominently in the meeting. The meeting was attended by Provincial Planning Minister Syed Nasir Hussain Shah, Local Government Minister Saeed Ghani, Irrigation Minister Jam Khan Shoro, Water and Power Development Authority (Wapda) Chairman Naveed Asghar Chaudhry, Sindh Chief Secretary Rahim Sheikh and senior officers. The meeting took place after a visit to the K-IV project by Wattoo, along with provincial Planning Minister Nasir Shah. The meeting was informed that with 63% construction work finished, the project's Phase I would be completed next year. The water requirement of Karachi, at present, is 1,300 million gallons per day (MGD). However, the city receives half of its needs – 650 MGD. To meet the shortage, the Sindh government planned K-IV project to supply 650 MGD from Keenjhar Lake to the city. WAPDA is working on Phase-1 of the project, following its approval from the Executive Committee of the National Economic Council (ECNEC) in January 2022 at a cost of Rs126.404 billion. Despite administrative approval, the chief minister stated that the project faced challenges that needed federal intervention. Shah pointed out that the project required Rs39.964 billion funding during the current fiscal year, 2025-26, but the federal government had allocated Rs3.209 billion only. It could cause delays, risking cost escalation and contractor claims. Wattoo told the chief minister that he would brief Prime Minister Shehbaz Sharif regarding the project to secure additional funds. He acknowledged that Sindh had mostly resolved the Right of Way (ROW) issues but two major obstacles still remained – land acquisition in Thatta and a court case. The chief minister assured that the land for the pumping station in Thatta would be handed over soon. He also assured the federal government of the release of Rs8.5 billion as part of the fourth quarterly instalment in Sindh's share of funding in the project. Chief Minister Shah said that Sindh had repaired the old Hub Canal and built a new 100 MGD-capacity channel to improve water supply to Karachi. Both leaders agreed to conduct a technical survey to assess water availability before submitting recommendations to the Council of Common Interests (CCI). Inter-provincial water distribution The chief minister urged the federal minister to facilitate a direct meeting between Sindh and Punjab's irrigation departments to resolve the water-sharing disputes. He emphasised that water distribution must be done under the 1991 Water Accord. Chief Minister Shah recalled that the CCI had tasked the then attorney general for Pakistan with reviewing the accord during the tenure of former prime minister Shahid Khaqan Abbasi. Wattoo agreed to hold separate meetings with representatives from both provinces.


Business Recorder
a day ago
- Business Recorder
Minister visits K-IV project to review progress
LAHORE: Federal Minister for Water Resources Mian Muhammad Mueen Wattoo visited Greater Karachi Bulk Water Supply Scheme (K-IV Project) and reviewed the ongoing development works on the project. The federal minister visited in detail various key work fronts, which included intake structure and pumping stations being constructed at Keenjhar lake, water conveyance system consisting of pressurized pipeline from Keenjhar to Karachi as well as water reservoirs and filtration plants in suburbs of Karachi. During the visit, the federal minister was briefed by the project team about the site-wise progress achieved so far, remaining works and timelines for their completion. It was briefed that construction work on all components of the project is in progress at a satisfactory pace. Overall physical progress stands at 63 percent, while a sum of Rs 86.4 billion has so far been spent on construction of the project. Phase-I is planned to be completed in 2026, provided the required funds are made accordingly. Speaking on the occasion, the federal minister expressed satisfaction over the pace of work and reiterated the federal government's full support for the project. K-IV is a vital scheme for supplementing water supplies to Karachi to meet water requirements for the urban use. 'We are committed to ensuring completion of K-IV at the earliest as it is one of the priority projects of the Ministry of Water Resources,' he added. The minister emphasized the need for enhanced coordination among all stakeholders to remove bottlenecks for smooth implementation of the project. He also directed the consultants and the contractors to adhere to the quality standards stipulated for the project. The K-IV project is a critical infrastructure initiative aimed at addressing Karachi's acute water shortage by providing an additional 650 million gallons per day (MGD) water to Karachi from Keenjhar lake. The project is planned to be completed in two phases. At present, WAPDA is constructing Phase-I of to supply 260 MGD water to Karachi. Phase-II, when implemented, will also augment another 390 MGD water to the system for Karachi. Phase-I is being implemented through eight contract packages awarded to different local and international contractors. Copyright Business Recorder, 2025


Business Recorder
a day ago
- Business Recorder
Iesco, Fesco and Gepco set for sell-off by Dec-end
ISLAMABAD: Three electricity distribution companies - Iesco, Fesco and Gepco - will be ready for privatisation by the end of December this year. This was stated by an official of the Power Division in the National Assembly Standing Committee on Economic Affairs' meeting held under the chairmanship of Muhammad Atif Khan. Additional Secretary Power Division Mehfooz Bhatti, in his presentation, told the committee that along with Privatisation Commission, the Power Division is working on the privatisation of all 10 Discos. He said that the privatisation process of Islamabad Electric Supply Company (Iesco), Gujranwala Electric Power Company (Gepco) and Faisalabad Electric Supply Company (Fesco) is already in advance stage. 'The due diligence process of these three Discos is in final stage and Financial Advisor has also been hired,' he said. The official said as per his information, the Privatisation Commission is working on the financial structure and by December this year, Expressions of Interest (EOIs) would be invited and terms and conditions of sale purchase agreement will also be finalised. Chairman Committee Atif Khan said that no one is stopping the government from privatising the Discos but it does not mean hiring in these Discos should be stopped. He said in his constituency for hundreds of kilometers there is only one lineman and because of this people were facing a lot of hardship in getting their complaints addressed. The Power Division official clarified that their ministry did not stop any Disco from hiring necessary staff. MNA Sher Ali Arbab said that as per his knowledge there are 80,000 vacancies in all 10 Discos but Prime Minister Shehbaz Sharif has given approval to hire only 20,000-25,000 personnel to keep things afloat. Members, unanimously, expressed concern over the methodology that exclusively targets Discos with minimal transmission and distribution losses for privatisation. The committee emphasised that by limiting privatisation to only the most efficient utilities, the government would be compelled to retain chronically underperforming Discos, thereby, exacerbating existing operational challenges and making their eventual privatisation virtually unattainable. The Power Division official informed the committee that their current installed capacity is 39,952 MW that includes 46 percent from clean energy and 54 percent from fossil. The power sector informed that there is overreliance on fossil than clean energy. The Power Division presented a comprehensive overview of Pakistan's current power generation capacity to the Standing Committee, reporting a total installed capacity of 39,952 MW. The energy mix analysis revealed a concerning imbalance, with fossil fuel-based generation accounting for 54 percent compared to just 46 percent from clean energy sources. The committee was informed that Pakistan's power sector currently faces a significant surplus of approximately 7,000 to 8,000 MW in electricity generation capacity. Members expressed serious concern over the substantial financial burden imposed by capacity payments for this unused electricity, which continues to strain the national exchequer despite serving no practical purpose. The committee members raised serious concerns regarding the inequitable distribution of development projects and budget allocations for Khyber Pakhtunkhwa in the proposed federal budget for 2025-26. The committee noted with concern that while KP has a substantially larger population than Gilgit-Baltistan (GB), both regions have been allotted only two new projects each, reflecting an unjust disparity. Furthermore, the budgetary allocations for development projects across provinces revealed that Balochistan receiving Rs209.6 billion, Punjab Rs76.6 billion, Sindh Rs145.9 billion, and KP Rs30.843 billion. The Economic Affairs Division (EAD) informed the committee that it has filed appeals and interim relief applications, with hearings ongoing and the next scheduled for September 2025. Meanwhile, the EAD has sought the federal cabinet's in-principle approval for a new legislative framework, the 'Foreign Contributions (NGOs and NPOs) Regulation Act, 2025,' to address the legal gaps. Copyright Business Recorder, 2025