Pasir Gudang Highway upgrade: Phased opening confirmed as RM301m project nears completion
Johor Public Works, Transport, Infrastructure and Communications Committee chairman Mohamad Fazli Mohamad Salleh said the road opening would be carried out in stages involving several sections along the five-kilometre work area, depending on the level of readiness and current safety aspects.
'This will allow the completed sections to be opened earlier so that the public can begin using them and enjoy the benefits.
'If we want to expedite the project, we would have to open only one lane while work is ongoing. However, that would cause traffic disruptions. So, we need to strike a balance...it cannot be reduced to fewer than the two lanes currently in use,' said the Bukit Pasir Assemblyman, who visited the site to see the work progress of the project last night.
Commenting on the latest development at the project site, Mohamad Fazli said his primary focus was on two key locations – at CH1170 (in front of Petron) and CH4200 (near the Wau replica roundabout), as these areas were riddled with potholes, poorly lit and had uneven road surfaces.
He said that works such as road surfacing and lighting installation were being actively carried out, with over 467 patching works completed since January.
The contractor, he said, had also given an assurance that the installation of 197 streetlights along the five-kilometre route would be completed by July 11, complemented by additional spotlights and warning blinkers at blind spots to enhance road user safety.
Meanwhile, Mohamad Fazli said motorists whose vehicles were damaged due to potholes along the project route could file a compensation claim to the contractor or concessionaire.
'This provision is part of the contract between the Public Works Department (JKR) and the concessionaire. The road must be maintained in a safe condition at all times. If damage or an accident occurs due to unsafe infrastructure, road users can lodge a police report and submit a claim with photographic evidence of the incident location,' he said.
The Pasir Gudang Highway serves as the main route to Pasir Gudang, the largest industrial area in the country, which is home to more than 5,000 factories across various industries. It also connects two major ports – Johor Port and Tanjung Langsat Port (PTL).
Menteri Besar Datuk Onn Hafiz Ghazi announced last February that the Pasir Gudang Highway upgrading project (Phase 3), involving the stretch from the Perling Elevated Interchange to the North-South Expressway On-ramp, would see the highway expanded from four lanes to six lanes at a cost of RM301.5 million.
The project is expected to be completed by June 2028.
Meanwhile, the project to upgrade the Pasir Gudang Highway (Phase 2B), covering the stretch from the Bandar Seri Alam/Taman Rinting Interchange to Pasir Gudang, will also be widened from four lanes to six lanes at a cost of RM78 million. It is scheduled for completion by February 2026. — Bernama
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

Malay Mail
an hour ago
- Malay Mail
JPJ recalls over 8,000 Kia, Yamaha, Mercedes-Benz vehicles over fire risk, clutch and fuse defects
PUTRAJAYA, July 9 — The Road Transport Department (JPJ) has recalled 8,322 Kia, Yamaha and Mercedes-Benz vehicles for inspection following defects to the structure, equipment or systems. Its director-general, Aedy Fadly Ramli said that the Kia vehicle involved in the recall was 5,123 units of the Rio UB 2010 to 2017 model, suspected to have the risk of shortcircuit that can cause its Hydraulic Electronic Control Unit (HECU) to catch fire. Also, 1,649 units of Yamaha MT09 and 1,369 units of Tracer 9 GT from November 2021 to Februari 2025 are being recalled for improper functioning Throttle Position Sensors (TPS), while 149 units of the Yamaha Tenere 700 model from 2023 to 2024 are being recalled for clutch problems. A total of 32 Mercedes-Benz cars, model S 580 e, GLC 300 4MATIC, EQS 500, AMG SL 43, EQE 53 and EQS 53 from 2023 and 2025 are being recalled for improperly installed fuse boxes. 'The recall is important to avoid crashes due to defects,' he said in a statement yesterday, adding that owners would be contacted by the respective manufacturers to coordinate inspection slots. 'All owners with affected models are asked to plan ahead to enable the recall and inspection to be done as soon as possible. 'For further information, owners can contact or visit any sales and service centre,' he said. Aedy Fadly also said that all components affected will be replaced with the costs borne by the manufacturer. 'The JPJ will monitor the process and remains committed to ensure all vehicles involved undergo inspection and are certified safe,' he added. — Bernama


Free Malaysia Today
15 hours ago
- Free Malaysia Today
Tokyo Auto Salon KL returns in August with bigger names, rare cars
Element X Strategies CEO and director Jason Yap (left) and Tokyo Auto Salon Federation director-general Junichi Fukui at a press conference at Mitec, Kuala Lumpur, today. KUALA LUMPUR : The third edition of Tokyo Auto Salon Kuala Lumpur (TASKL) will take place from Aug 8-10 at the Malaysia International Trade and Exhibition Centre (Mitec) here, with organisers promising a bigger show featuring rare car builds and a stronger fusion of Japanese and Malaysian automotive cultures. Among the headliners this year are six legendary names from Japan's tuning scene: Top Secret's Smokey Nagata, Liberty Walk's Wataru Kato, RE Amemiya's Isami Amemiya, KUHL Racing's Takahiro Kataoka, J's Racing's Hisaaki Murakami and Hiroshi Tamura, known as the father of the modern GT-R. Several iconic and rare vehicles will be flown in from Japan, including the one-of-a-kind Top Secret VR-32 Stealth Nissan GT-R, Liberty Walk's custom Ferrari F40, and the Super Silhouette ER34. Fans can also expect to see newer concept builds such as the CREWCH Delusion GT-R R356C and Matsukiyo Kizami 3Rotar NA-7. New to TASKL 2025 is a special showcase called Malaysia's Finest Tuners, which highlights the work of top local car builders and encourages collaboration between Japanese and Malaysian tuners. A die-cast collector's segment, the Mini TAS, will also be held in partnership with Model Car Show Malaysia. Jason Yap, CEO and director of Element X Strategies, said the event has grown steadily since its 2023 debut and continues to build its own identity. 'This year, we're focused on making the show even more accessible and even more memorable. We're not replicating the original Tokyo show, but creating something that belongs uniquely to Malaysia and the region,' he told a press conference at Mitec today. Element X Strategies is the official licensee of TASKL, working in collaboration with San Ei Corporation, the owner of the Tokyo Auto Salon intellectual property, and the Tokyo Auto Salon Association. Junichi Fukui, director-general of the Tokyo Auto Salon Federation, said the growing momentum of TASKL has led to new cross-border ventures. 'Japanese exhibitors have begun forming business partnerships with Malaysian companies as a result of this event,' he said. There will also be a lucky draw featuring a specially modified motorbike, with additional prizes such as tyres and other automotive products. A mix of local and international artistes will perform during the three-day show, with final confirmations to be announced on TASKL's social media channels. In the lead-up to the main event, TASKL will host the Prime Minister's Cup CSI1 — a SEA Games equestrian qualifier — from July 18 to 27 at the Kuala Lumpur Polo Club. On Aug 2, the Malaysia GT-R Festival will take place alongside the first official FL5 Type R track day at the Sepang International Circuit. TASKL tickets are priced at RM48 for a one-day adult pass, RM30 for children aged six to 12, and RM120 for a family combo pass. A three-day adult pass is also available, along with a 50% discount for persons with disability cardholders and their caregivers. Children aged five and below can enter for free. For tickets, updates and event information, visit or follow Tokyo Auto Salon Kuala Lumpur on Facebook, Instagram and TikTok.


New Straits Times
a day ago
- New Straits Times
Pasir Gudang Highway: Phased road opening expected soon
JOHOR BARU: Final discussions with contractors and related agencies are expected to conclude this week to finalise the location and date for the phased opening of the three-lane road under the Pasir Gudang Highway widening project. Johor Public Works, Transport, Infrastructure and Communications Committee chairman Mohamad Fazli Mohamad Salleh said the road opening would be carried out in stages involving several sections along the five-kilometre work area, depending on the level of readiness and current safety aspects. "This will allow the completed sections to be opened earlier so that the public can begin using them and enjoy the benefits. "If we want to expedite the project, we would have to open only one lane while work is ongoing. However, that would cause traffic disruptions. So, we need to strike a cannot be reduced to fewer than the two lanes currently in use," said the Bukit Pasir Assemblyman, who visited the site to see the work progress of the project last night. Commenting on the latest development at the project site, Mohamad Fazli said his primary focus was on two key locations - at CH1170 (in front of Petron) and CH4200 (near the Wau replica roundabout), as these areas were riddled with potholes, poorly lit and had uneven road surfaces. He said that works such as road surfacing and lighting installation were being actively carried out, with over 467 patching works completed since January. The contractor, he said, had also given an assurance that the installation of 197 streetlights along the five-kilometre route would be completed by July 11, complemented by additional spotlights and warning blinkers at blind spots to enhance road user safety. Meanwhile, Mohamad Fazli said motorists whose vehicles were damaged due to potholes along the project route could file a compensation claim to the contractor or concessionaire. "This provision is part of the contract between the Public Works Department (PWD) and the concessionaire. The road must be maintained in a safe condition at all times. If damage or an accident occurs due to unsafe infrastructure, road users can lodge a police report and submit a claim with photographic evidence of the incident location," he said. The Pasir Gudang Highway serves as the main route to Pasir Gudang, the largest industrial area in the country, which is home to more than 5,000 factories across various industries. It also connects two major ports — Johor Port and Tanjung Langsat Port (PTL). Menteri Besar Datuk Onn Hafiz Ghazi announced last February that the Pasir Gudang Highway upgrading project (Phase 3), involving the stretch from the Perling Elevated Interchange to the North-South Expressway On-ramp, would see the highway expanded from four lanes to six lanes at a cost of RM301.5 million. The project is expected to be completed by June 2028. Meanwhile, the project to upgrade the Pasir Gudang Highway (Phase 2B), covering the stretch from the Bandar Seri Alam/Taman Rinting Interchange to Pasir Gudang, will also be widened from four lanes to six lanes at a cost of RM78 million. It is scheduled for completion by Feb 2026. — BERNAMA