logo
South Delhi faces waterlogging threat as drain cleaning remains behind schedule

South Delhi faces waterlogging threat as drain cleaning remains behind schedule

Hindustan Times08-05-2025
New Delhi
South Delhi may be set for a repeat of waterlogging this monsoon, as three key drains — the Kushak drain and supplementary Sunehripul and Defence Colony drains — are yet to be desilted. The process may not be completed by the arrival of monsoon, typically the last week of June, according to an affidavit submitted by the Municipal Corporation of Delhi to the National Green Tribunal (NGT) earlier this week.
In its affidavit dated May 5, the MCD said efforts were being made to desilt the covered portion of all three drains, with progress varied for each drain. It said work on the 1.4-kilometre-long Sunehripul drain — which flows along Defence Colony and underneath Lala Lajpat Rai Marg before joining Barapullah drain — will be executed by the Delhi Metro Rail Corporation (DMRC), as decided by the lieutenant governor (LG) in a recent meeting, but desilting work was yet to begin.
'DMRC is to carry out the covered modification in the covered portion of drain and desilt it from the inlet at Dayal Singh College up to Lala Lajpat Rai Marg using appropriate methodology. As per the said direction, the chairman NDMC has already been formally requested to release the funds to the DMRC to enable the latter to take up the work,' it said in the affidavit, a copy of which was accessed by HT.
'The exact design contours of the work will be finalized by the DMRC,' it added.
Last week, NGT sought clear timelines from the MCD on when the desilting of the three south Delhi drains would be completed. It also asked the MCD to disclose the safety measures it will put in place after desilting, to ensure that the opening in the covered portion does not lead to an accident or emission of foul smell.
The three drains extend to around nearly 10km in length and traverse south Delhi neighbourhoods of Defence Colony, INA, Chirag Dilli, Nizamuddin, Jangpura, Pushp Vihar, Andrewsganj and Greater Kailash, among others.
In the affidavit, the MCD said work on the 6.5-km-long Kushak drain, which empties into the Barapullah drain, can only commence once work on the Sunehripul drain is complete. Here, nearly a one-kilometre-long stretch near the Kushak bus depot is covered, requiring intervention. 'That work on covered portion of Kushak drain having the DTC bus depot shall be taken up only upon stabilization and assessment of the work at Sunehripul as mentioned above,' MCD said in the affidavit.
Further, MCD said that around 1.3 kilometres of the 1.6-kilometre-long Defence Colony drain, a subsidiary of the Kushak drain, is covered. The civic agency said it planned to complete the longitudinal opening and desilting of the entire covered portion within 120 days, from the date of the award of work.
'The Notice Inviting Tender (NIT) has been issued and bids shall be received on May 10, 2025,' the affidavit said, adding that a 50-metre stretch has been opened so far. It said directions were issued to engineers-in-charge to target completing work on the opening and desilting a substantial portion of it by June 30, to curb waterlogging.
Generally, June 27 is considered the normal date of onset of monsoon in Delhi. The NGT has been hearing multiple pleas filed on Delhi's stormwater drains, with petitions from residents of Nizamuddin West, Defence Colony and Shahdara, among others across the city, seeking action against the sewage flowing through the Capital's drains. Multiple pleas pointed out that sewage flow caused foul smell and waterlogging during monsoon.
Last year, large parts of the Capital were waterlogged, largely owing to a lack of adequate desilting work. All drains in Delhi were eventually handed over to the irrigation and flood control (I&FC) department to reduce the multiplicity of agencies in the desilting exercise.
However, I&FC in March this year expressed concerns over desilting the covered portions of Kushak and Sunehripul drains. A month prior, the NGT said it was crucial to undertake desilting on time to avoid waterlogging. The initial deadline set to desilt all drains in Delhi, set by the I&FC is May 31, which is likely to be missed too.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

NGT pulls up MCD over failure to clean Aya Nagar pond, seeks affidavit from commissioner
NGT pulls up MCD over failure to clean Aya Nagar pond, seeks affidavit from commissioner

New Indian Express

time2 days ago

  • New Indian Express

NGT pulls up MCD over failure to clean Aya Nagar pond, seeks affidavit from commissioner

NEW DELHI: The National Green Tribunal (NGT) has come down heavily on the Municipal Corporation of Delhi (MCD) for failing to clean and restore a severely polluted pond in Aya Nagar, South Delhi, despite repeated directions and inspections by the Delhi Pollution Control Committee (DPCC). Taking suo motu cognisance of the matter, the Tribunal has now directed the MCD Commissioner to file an affidavit within four weeks explaining the prolonged inaction. The case was triggered by multiple inspection reports filed by the DPCC, which highlighted the alarming condition of the pond. The most recent report, submitted on June 11, 2025, following an inspection on May 13, noted that the pond remained filled with plastic waste, garbage, and sewage. Geo-tagged photos submitted by the DPCC confirmed dumping of waste along the pond's periphery, with the garbage ultimately contaminating the water. The area also emitted a strong foul smell, indicating the presence of untreated sewage. Crucially, water samples collected during the inspection failed to meet the prescribed standards for Biochemical Oxygen Demand (BOD) and Total Coliform levels, confirming high levels of contamination. 'The above report of DPCC was filed on or about June 11, 2025. Thereafter, more than one and a half months have passed, but MCD has not filed any response to the status noted in the report,' observed the Tribunal, pulling up the civic body for its 'complete failure' to comply with its earlier orders and to take necessary remediation steps. The issue dates back to November 2023, when the NGT had first directed the DPCC to inspect the pond and initiate remedial measures. A follow-up inspection in February 2024 had already revealed rampant pollution, including the dumping of plastic, washing of cattle nearby, and direct discharge of sewage into the water body due to lack of a functional sewerage system. Despite notices issued in August 2024 and a series of directions over the months, the MCD has remained largely non-responsive, according to the Tribunal's records. In its latest order, the NGT said: 'We require the Commissioner, MCD to file an affidavit disclosing the reasons for not taking steps to keep the pond clean and failing to restore the pond and not complying with the orders of the Tribunal.' The next hearing is scheduled for August 25, 2025. Environmental activists have called the situation a reflection of civic apathy. Case triggered by multiple inspection reports by DPCC The case was triggered by multiple inspection reports filed by the DPCC, which highlighted the alarming condition of the pond. The most recent report, submitted on June 11, 2025, following an inspection on May 13, noted that the pond remained filled with plastic waste, garbage, and sewage. Geo-tagged photos submitted by the DPCC confirmed dumping of waste along the pond's periphery, with the garbage ultimately contaminating the water. The area also emitted a strong foul smell.

Delhi govt to notify Southern Ridge after verification of villages
Delhi govt to notify Southern Ridge after verification of villages

Hindustan Times

time2 days ago

  • Hindustan Times

Delhi govt to notify Southern Ridge after verification of villages

The Delhi government's department of forests and wildlife has informed the National Green Tribunal (NGT) that it has begun an on-ground verification across 12 villages in the Southern Ridge, which will pave the way for final notification under Section 20 of the Indian Forest Act, 1927. The government told NGT that a crucial joint ground verification exercise is underway across 12 villages. (FILE) Sharing detailed timelines which will see verification be completed across a majority of the villages before the end of the year, the department in its affidavit said that a detailed demarcation was last carried out in 2019. This comes in compliance with a July 4 NGT directive. Delhi's Ridge areas have already been notified under Section 4 of the Indian Forest Act, 1927. However, the final notification under Section 20 is yet to be completed, which grants complete protection and defines the boundaries. The affidavit, filed by Shyam Sundar Kandpal, principal chief conservator of forests and head of department, outlines that a crucial joint ground verification exercise is underway across 12 villages. This comes after a high-level meeting was chaired by the lieutenant governor on May 23 this year, where it was decided that the revenue and forest departments must verify that the areas are free from encroachments before the final notification. 'In order to minimise potential discrepancies or errors in demarcation and need for identification or verification of encroachment, the Government has directed the Revenue Department, Government of National Capital Territory of Delhi (GNCTD), along with the Department of Forests and Wildlife, GNCTD to jointly conduct a ground verification exercise for the area proposed,' the affidavit mentions. The affidavit includes a detailed timeline for completing the verification village-wise, coordinated by respective district magistrates and subdivisional magistrates. Surveys of villages in Saket division, namely Sahoorpur and Asola, are expected to be completed between July and August. Survey of Neb Sarai is slotted for September, Maidangarhi in September and October, Satbari in November and Bhati will be surveyed in December and January 2026. In Mehrauli, Dera Mandi ground verification is scheduled in August and September , Aya Nagar in October and November, and Jonapur in December and January 2026. Ghitorni and Rajokri are expected to be completed by August, along with Tughlakabad. The forest department has pledged to finalise notifications immediately after ground verification and has requested the tribunal to allow six months for completing this exercise. Delhi has four prominent Ridge areas, with the total area under the Ridge as reserved forests totalling around 7,784 hectares. The largest – the southern Ridge is spread over an area of 6,200 hectares.

How pollution fight took a backseat, thanks to a typo
How pollution fight took a backseat, thanks to a typo

Time of India

time2 days ago

  • Time of India

How pollution fight took a backseat, thanks to a typo

Noida: Residents of an Indirapuram housing society had to bear the brunt of two noisy, polluting diesel generators (DG) for two years even after an NGT directive, allegedly over a "typographical error". Over two years after the case pertaining to DG sets near Nirala Eden Park in Indirapuram came up before NGT, the tribunal directed GMC to replace them within three months. DGs were found to be "causing pollution and inconvenience" to residents. The two-year delay is not on the part of NGT or UP Pollution Control Board (UPPCB). In fact, NGT had given directions to UPPCB in 2023 Feb and even UPPCB had given its report and recommendations in July 2024. You Can Also Check: Noida AQI | Weather in Noida | Bank Holidays in Noida | Public Holidays in Noida A "typo" in the July directive of UPPCB has been used by GMC to escape the onus of timely compliance. The matter had been registered in 2023 on the basis of a letter written to the tribunal by the secretary of the Nirala Eden Park Residents Welfare Association, raising a grievance about "foul-smelling hazardous gases being emitted from the sewage pumping station (SPS) and noise pollution from the high-power DGs" installed in the sewage plant situated just adjacent to the society's boundary wall. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Get Fast, Secure Gold Loans, Trusted By Millions Since 1949 Manappuram Finance Learn More Undo The residents endured the pollution and noise despite a recommendation sent by UPPCB to GMC July 2024 due to a small typographical error. Appearing before the commission on July 16, counsel for GMC said it could not comply with the recommendations as there was some "incorrect information". The counsel said, "The needful in compliance with the report of the UPPCB — dated July 10, 2024 — could not be done till now to replace the two DG sets at the 56 MLD sewage pumping station because, in para 2 (ii) of the report of the UP PCB, a factually incorrect assertion has been made that the DG sets in the SPS are of 320 KVA each, whereas these DG sets are of 750 KVA each. " NGT said that since the counsel appearing for the UPPCB has not disputed the claim, the municipal corporation should now proceed with compliance. The tribunal comprising chairperson Justice Prakash Srivastava and expert members Dr A Senthil Vel and Dr Afroz Ahmad said, "UPPCB counsel submits that it's an inadvertent typographical error. Hence, the municipal corporation is permitted to proceed on the basis of the above correction and take necessary action to comply with the report of the UP PCB in respect of the replacement of the DG sets as also in other aspects. " Disposing of the matter on Feb 22, 2023, the tribunal had directed the UPPCB to take action, if necessary, and submit an action-taken report. Responding to the direction, UPPCB filed its report before NGT, saying two main SPSs with capacities of 56 MLD and 48 MLD are established adjacent to the boundary wall of the said society and were reported to be operated by the private agency M/s VA Tech Wabag Ltd., Chennai. "The 56 MLD main sewage pumping station has six pumps with a capacity of 220 HP each for pumping sewage coming from nearby areas. It has two DG sets (320 KVA each) with acoustic enclosures but inadequate stack height. These DG sets are also not converted into dual fuel in compliance with CAQM directions, while the 48 MLD main sewage pumping station has four pumps. It has two DG sets (700 KVA each) and both are very old and must be replaced," UPPCB said.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store