86% of work done to repair Lilian Ngoyi Street: CoJ

86% of work done to repair Lilian Ngoyi Street: CoJ

Eyewitness News17 hours ago
JOHANNESBURG - The City of Johannesburg said repairs to the damaged Lilian Ngoyi Street in the CBD are close to completion, with 86% of the work done.
A portion of the corridor has been closed off to traffic for two years, due to an underground gas explosion that damaged the street.
Delays to fixing the road were caused by disputes with the previous contractor, who was replaced with a new company late last year.
ALSO READ: Morero says hefty funds to repair Lilian Ngoyi Street will also be used to upgrade corridor
Johannesburg Roads Agency CEO Zweli Nyathi said repairs would be completed by the end of this month.
'Despite adverse weather conditions earlier in the year, the contractor at the Lilian Ngoyi site has demonstrated exceptional performance, maintaining project timelines through a revised and accelerated exception programme.
The City of Johannesburg said only R64 million has been used so far to repair the street, and almost R200 million has been allocated to fix it.
The remaining money will be used for phase two of the project. The second phase will focus on enhancing the aesthetic appeal of Lilian Ngoyi Street once the repairs are finalised.
Nyathi said his teams have been hard at work to ensure the road is reopened to traffic at the end of this month.
'The team has ensured minimal disruption to pedestrian flow and surrounding commercial activity. This is a testament to strong project coordination and adaptive planning in partnership with JRA.'
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

After the Bell: SA's economy — it's the politicians, stupid
After the Bell: SA's economy — it's the politicians, stupid

Daily Maverick

time5 hours ago

  • Daily Maverick

After the Bell: SA's economy — it's the politicians, stupid

The main reason the US tariffs are having such a big impact on us is because we're so weak, yet our leaders seem impotent in the face of it. In the past couple of weeks, friends of mine who have come to Joburg for business or a meeting (or, in one brave case, to actually find a house to buy because they're moving back) have all used the same phrase to describe the city. They say, with some feeling, it's like 'a war zone'. What they're really pointing to is the visible damage to the city, the potholes that have been there for so long they have plants, trees and, in at least one case, a birthday party. And, of course, treated, drinkable water just flows down the street because Joburg Water is such a mess. At the same time, every minister and official and political person is now talking about the US tariffs. And watch, in about five minutes after you read this, they're going to start blaming the tariffs for our economic situation. Actually, it's really them. On Monday night, the Mpact CEO Bruce Strong told me on The Money Show that in the six months to the end of June, their facility in Ekurhuleni had been without power for 18 days. This is a 24-hour factory. It produces packaging and paper. Can you imagine workers sitting around with nothing to do for 54 whole shifts? It's the same in the Eastern Cape. For all of the tears being spilt around our car industry and the factories there, so many of their problems are really about local government. But no, we will be told it's the impact of the US tariffs. And, of course, as we all know, almost every council outside the Western Cape just can't manage their money. It's now at the point that National Treasury has in effect told the Joburg mayor, the ANC's Dada Morero, that it will refuse to pay some of their national grant, simply because Morero has done nothing to sort out how the money is treated. The coalition in Joburg is so fragile that Morero has not even appointed a new mayoral committee member for finance. Now, some of the smaller parties are demanding that their candidate, Kabelo Gwamanda from Al Jama-ah, must get the job. Just imagine this for a minute. You have a group of parties, some of them with just one councillor, insisting that their person take over the finance role in the country's biggest city. Knowing all along that they are largely responsible for the situation we find ourselves in. Last night, the ANC finally finished its long-postponed NEC meeting. One of its proclamations was that we are now in an 'economic state of emergency'. My first thought was that they had stolen the idea from Lesotho. Obviously, you have to ask yourself: How did it happen? Does the ANC really understand the role that its economic policy, and our broken politics generally, has played in this? Of course, you cannot blame one party. If you look at all of our neighbours, they have almost exactly the same unemployment rate as ours. Even Botswana, which so many kept saying was run so well for so long. Over the past couple of days, plenty of good well-meaning people have made the same point: we need a national effort, we need to work together to fix our economy. And, obviously, they're right. The main reason the tariffs, and everything else that is happening in the world (and it's a long list at the moment), are having such a big impact on us is because we're so weak. And yet, strangely, our leaders seem, well, impotent in the face of it. We need action, not a 'National Dialogue'. I can't believe I have to say this out aloud. But the one thing we absolutely do NOT need to do is talk. Now, I hate to have to say this, but do you believe there is any reason this is going to improve? Me too. Instead, what I think is going to happen is that our politicians, each chasing a smaller sliver of support, are going to shout and scream, and try to make it all about them. My greatest fear is that, in fact, we will end up with a national government in the future that is a lot like Joburg's now. Of course, nothing is predestined. There can be a lot of change. And, considering the nature of our society, there probably will be. But when our politicians start to blame the US, or Trump, or whoever, for our economic situation, we must remind them who is really responsible. It's the politicians. Not us. DM

86% of work done to repair Lilian Ngoyi Street: CoJ
86% of work done to repair Lilian Ngoyi Street: CoJ

Eyewitness News

time17 hours ago

  • Eyewitness News

86% of work done to repair Lilian Ngoyi Street: CoJ

JOHANNESBURG - The City of Johannesburg said repairs to the damaged Lilian Ngoyi Street in the CBD are close to completion, with 86% of the work done. A portion of the corridor has been closed off to traffic for two years, due to an underground gas explosion that damaged the street. Delays to fixing the road were caused by disputes with the previous contractor, who was replaced with a new company late last year. ALSO READ: Morero says hefty funds to repair Lilian Ngoyi Street will also be used to upgrade corridor Johannesburg Roads Agency CEO Zweli Nyathi said repairs would be completed by the end of this month. 'Despite adverse weather conditions earlier in the year, the contractor at the Lilian Ngoyi site has demonstrated exceptional performance, maintaining project timelines through a revised and accelerated exception programme. The City of Johannesburg said only R64 million has been used so far to repair the street, and almost R200 million has been allocated to fix it. The remaining money will be used for phase two of the project. The second phase will focus on enhancing the aesthetic appeal of Lilian Ngoyi Street once the repairs are finalised. Nyathi said his teams have been hard at work to ensure the road is reopened to traffic at the end of this month. 'The team has ensured minimal disruption to pedestrian flow and surrounding commercial activity. This is a testament to strong project coordination and adaptive planning in partnership with JRA.'

Lilian Ngoyi Street rehab on track to wrap phase 1 by end of August
Lilian Ngoyi Street rehab on track to wrap phase 1 by end of August

The Citizen

time2 days ago

  • The Citizen

Lilian Ngoyi Street rehab on track to wrap phase 1 by end of August

The second phase of the rehabilitation is set to begin in September and continue until August 2026. The City of Johannesburg has confirmed that the rehabilitation of Lilian Ngoyi Street in the inner city is progressing well and remains on track to meet its end-of-August deadline for the completion of Phase 1. The Johannesburg Roads Agency (JRA), which is overseeing the R192 million project, announced on Monday that 86% of the construction scope between Harrison and Kruis streets has already been completed. 'The contractor has performed exceptionally well in ensuring that the projected timelines are met, despite adverse weather conditions earlier in the year,' said JRA CEO Zweli Nyathi. Tunnels built, safety systems underway Key structural elements such as reinforced tunnel construction, backfilling, and compaction have been completed. The JRA is now focusing on finalising pavement layers and installing critical safety infrastructure, including gas, heat, and smoke detection systems. These systems, currently 60% complete, are designed to monitor gas build-up and ventilate tunnels, a safety measure aimed at preventing future gas-related incidents. To fast-track progress, construction hours have been extended, including work on weekends and evenings, to minimise disruption to pedestrian and business activity. 'A robust work plan was developed by extending the daily construction hours. 'Additionally, pavement construction work is undertaken in the evenings to ensure minimal foot-traffic disturbance,' Nyathi explained. ALSO READ: When will Johannesburg's M1 be painted? Jobs and SMME boost So far, R64 million has been spent on the first phase of the project. The city said the project has also created economic opportunities, with 27 Small, Micro and Medium Enterprises (SMMEs) benefitting and 38 general workers currently employed on site. Lilian Ngoyi Street and the affected north-south roads, Joubert, Rissik and Eloff streets will reopen to traffic once Phase 1 is completed. ALSO READ: No budget, no bridge, no answers from JRA Phase 2 to reshape Phase 2 of the rehabilitation is set to begin in September and continue until August 2026. According to JRA, it will focus on the upgrade of an additional 1.8km stretch between Ntemi Piliso and End Streets. 'This phase of the project adopts the City of Johannesburg's Inner City Transport Master Plan, which involves the improvement of public transport services and pedestrian mobility,' said the agency. Plans include wider walkways, safer passenger loading zones, and the development of a transit mall. ALSO READ: Smart number plates and 25-year vision: Here is Gauteng's roads budget Rolling closures and detours ahead To reduce traffic disruption during Phase 2, the City will implement a block-by-block closure system to allow for periodic refurbishment and continuous flow along intersecting roads. Detour details include: East to West: Sectional closures from Loveday Street to Miriam Makeba Street in Newtown. Alternative routes: Rissik, Loveday, and Rahima Moosa streets. West to East: Closures between Wanderers and Claim streets, with traffic rerouted via Wanderers, Plein, and Claim streets. The JRA extended gratitude to residents, road users, and business owners in Wards 59 and 60 for their cooperation. 'JRA thanks road users, residents, business operators and other stakeholders in Wards 59 and 60 for their continued patience and cooperation throughout the duration of both phase 1 and 2 of the project,' the agency concluded. NOW READ: Mind the hole: Good news in Johannesburg's pothole crisis

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store