Forensic report urges action against IDT execs over R800m oxygen tender
Macpherson released the findings of the independent forensic investigation on Tuesday. The report recommended disciplinary action against IDT CEO Tebogo Malaka, general manager for supply chain management Dr Molebedi Sisi, and other officials.
The IDT is a public entity established to deliver social infrastructure such as schools, police stations and clinics and falls under the department.
In October last year, the Daily Maverick published a series of articles 'surrounding the R836m oxygen plant tender', describing the IDT as the implementing agent in a multimillion-rand contract with the department of health for the rollout of pressure swing adsorption (PSA) oxygen plants.
Macpherson said the tender was intended to deliver life-saving PSA oxygen plants to 60 hospitals across the country. He said it was a project worth R836m, of which R528m had been allocated directly to the IDT for implementation.
Investigations by Daily Maverick and amaBhungane revealed that two of the companies awarded tenders lacked the necessary SA Health Products Regulatory Authority (SAHPRA) registration, raising red flags over basic compliance.
The Sunday Times reported that later in November, a ghost company with fraudulent documentation had been awarded a R428m share of the PSA oxygen plant tender.
Macpherson took his concerns to President Cyril Ramaphosa and called for the immediate suspension of the tender. This led to the department of health withdrawing the contract from the IDT, and announcing its intention to investigate how the tenders were awarded.
In January, Macpherson appointed an independent advisory firm to conduct a full, independent forensic investigation into the tender.
Reporting back on Tuesday, Macpherson said the report by investigators confirmed that multiple companies awarded work under the PSA project did not have valid SAHPRA licences.
'One company, Bulkeng (Pty) Ltd, submitted a SAHPRA licence belonging to Atlas Copco Industrial SA — without the knowledge or consent of Atlas Copco. This was a clear misrepresentation. It was fraud. Moreover, Bulkeng intended to subcontract more than 25% of its responsibilities to Brutes Air Solutions, but failed to disclose this, in violation of the preferential procurement regulations,' Macpherson said.
The investigators also found that the bid evaluation process was deeply flawed.
'The SAHPRA compliance requirement — originally stipulated in the project execution plan and the department of health's memorandum of agreement — was deliberately removed from the final request for proposals. This opened the door for ineligible bidders to participate and win huge contracts.
'Meeting minutes were missing or incomplete, which is shocking but not surprising. Committee appointments were not properly constituted. Bid scores were not properly documented. Price negotiations were not transparent,' he said.
Giving an example, Macpherson said the original department of health budget was R216m — but when the IDT issued the request for quotation, prices had ballooned to more than R590m without a single documented approval or value-for-money assessment.
Macpherson said Bulkeng's CIDB grading limited it to contracts of no more than R200m yet the IDT awarded it contracts worth R428m, more than double its allowable threshold.
He said Malaka, as the CEO of the IDT, failed to exercise oversight as the report confirmed she relied entirely on internal supply chain management staff to assure her that the process had followed proper procurement protocol. She failed to verify any of the documentation.
'She did not act on the red flags raised by the department of health. She did not convene the necessary risk committees to assess the matter. In this, she was not alone,' Macpherson said.
The report also singled out Sisi for his role in misleading internal stakeholders and failing to act per his responsibilities.
The forensic report recommended that disciplinary action should be taken against Malaka and Sisi. The investigation also recommends disciplinary referrals against several other IDT executives and supply chain management officials.
Macpherson said he has written to the Hawks, briefed the minister of health and met the newly appointed IDT board to initiate consequence management.

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles

IOL News
2 hours ago
- IOL News
Public Works makes strides in reducing rental payments owed to landlords
Public Works and Infrastructure Minister Dean Macpherson says his department has put in controls that were monitored daily and were aimed to improve the functioning of their payment systems. Image: Henk Kruger / Independent Newspapers Public Works and Infrastructure Minister Dean Macpherson said his department has managed to reduce to R20 million outstanding rentals owed to landlords that dated back three months ago. Macpherson said the department has put controls that are monitored daily and is looking at systems to improve the functioning of its payment systems. 'As at 6 June 2025, the outstanding rental amount is R2,540,382.42 (0.5%) and R19,897,707.26 (4.1%) for April and May, respectively,' he said. Macpherson was responding to parliamentary questions from Build One South African leader Mmusi Maimane, who enquired about the Information and Communication Technology outages that affected the ability of the Property Management Trading Entity to process rental payments to landlords in April. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Maimane enquired about the current status of rental payments, the total number of landlords that remained, the total monetary value of outstanding rental payments, and steps his department has taken to ensure that such delays do not recur. Macpherson said there were 1,991 leases for 1,274 landlords valued at R484,425,687.62 in the lease administration system and the payment system for April rental payments as of June 6. 'Forty-four leases (2.2%) affecting 26 landlords (2%) amounting to R2,540,382.42 (0.5%) failed Central Supplier Database (CSD) verification and therefore were not paid.' He also said there had been 1,995 leases for 1,269 landlords valued at R483,952,863.48 for May. At least 89 leases (4.5%) affecting 75 landlords (5.9%), amounting to R19,897,707.26 (4.1%) were not verified and were not paid. Macpherson said the payment system was still processing the June rental payments. 'The outstanding rental payments for April 2025 are 44 leases (2.2%) affecting 26 landlords (2%). The outstanding lease payments for May are 89 leases (4.5%) affecting 75 landlords (5.9%),' he said. 'It must be noted that the non-payment of transactions submitted on the payment system is primarily due to landlords not being compliant with CSD. In addition, 33 CSD non-compliant landlords from April are included in the May figure.' Meanwhile, the Independent Development Trust (IDT) has collected R882 million in payments in just three months from 15 departments that owed for infrastructure projects it implemented on their behalf. 'The IDT has been able to collect R882,374,561 between 01 April 2025 and 30 June 2025,' Macpherson said. The entity has paid a total of 1,366 service providers to the tune of R648,167,277. 'As at 30 June 2025, 790 service providers remained unpaid an amount of R1,394,036,545. The variance in the amount is due to additional invoices that would have been received between 01 April 2025 and 30 June 2025,' he said. Macpherson was responding to ActionSA MP Malebo Patricia Kobe, who enquired about the department's obligation to pay contractors after receiving money due from client departments. The IDT had informed the portfolio committee in June that it was owed R1.2 billion by client departments. It informed Parliament four months ago that it had been unable to pay service providers due to delays in payment by client departments. The entity has incurred R47m in total expenditure on legal costs and owed creditors for more than 12,000 invoices that could not be paid within the 30-day deadline as of the end of March last year.

TimesLIVE
a day ago
- TimesLIVE
PSA urges suspension of IDT officials over oxygen plant tender
The Public Servants Association (PSA) has called for the immediate suspension of Independent Development Trust (IDT) officials implicated in alleged misconduct in the R800m oxygen plant tender, pending the outcome of investigations. The PSA said it was outraged by revelations of alleged fraud and gross mismanagement in the R836m pressure swing adsorption oxygen plant project, overseen by the IDT. Public works and infrastructure minister Dean Macpherson released the findings of an independent forensic investigation on Tuesday. The investigation report recommended disciplinary action against IDT CEO Tebogo Malaka, GM for supply chain management Molebedi Sisi and other officials. The union said the project that aimed to install oxygen plants at 60 hospitals nationwide was seen as an opportunity for self-enrichment by greedy employees and service providers. 'What began as a R216m initiative to install life-saving oxygen plants at South Africa's public hospitals has inexplicably ballooned to R836m. This staggering escalation, reportedly owing to irregular procurement processes and cost overruns, is a grave betrayal of public trust and a direct threat to the integrity of South Africa's healthcare system.' The forensic investigation further revealed several companies were awarded contracts without having valid South African Health Products Regulatory Authority licences. The PSA condemned the apparent disregard for due process and fiscal responsibility, particularly in a sector as critical as public health. With millions of South Africans relying on state healthcare, every misallocated rand undermines the quality of care and endangers lives, it said. 'While investigations are under way, there is a need to implement stricter procurement and project management protocols to prevent further abuse of public resources.'

IOL News
a day ago
- IOL News
Motsoaledi welcomes forensic report clearing Health Department in R800m oxygen tender fraud
Minister of Health Dr Aaron Motsoaledi welcomes the release of the PSA Oxygen Plant tender report, reaffirming the Department's integrity and commitment to delivering oxygen infrastructure to 55 hospitals across South Africa. Image: GCIS A long-awaited forensic investigation into the R800 million Pressure Swing Adsorption (PSA) Oxygen Plant tender has uncovered shocking levels of fraud and governance failures within the Independent Development Trust (IDT), threatening one of South Africa's most critical public health infrastructure projects. Now, with the cloud of corruption beginning to lift, Health Minister Dr Aaron Motsoaledi says the path is finally clear to deliver life-saving oxygen infrastructure to 55 hospitals across the country. The forensic report, commissioned by Public Works and Infrastructure Minister Dean Macpherson, comes after months of public scrutiny over potential corruption linked to the project's original procurement process through the Independent Development Trust (IDT). Minister Motsoaledi lauded the transparency brought by the investigation, stating: 'I am pleased to note that a credible forensic investigation has gotten to the bottom of this matter to bring this matter to a close.' The report clears the Department of Health of any financial wrongdoing, a relief for a ministry that has relied on international partnerships, including donor funding from the Global Fund, to bolster the country's public health system. 'I am also satisfied that the report has not pointed any fingers at the Department of Health for any financial misdemeanour that may cast aspersions on the integrity of the department, because \[that] would have soured our relationship with the Global Fund,' Motsoaledi added. While the report does identify individuals who acted unlawfully, the Minister emphasised the serious consequences of their actions. 'They did not just commit financial corruption but deprived South Africans of urgent life support in the form of oxygen. As such, the Department of Health would like to see people being held to account and the law taking its course.' Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Next Stay Close ✕ The PSA Oxygen Plant project was swiftly moved from the IDT to the Development Bank of Southern Africa (DBSA) in a bid to restore confidence and ensure uninterrupted delivery. That decision, taken jointly by Ministers Motsoaledi and Macpherson when corruption concerns first surfaced, appears to have paid off. Motsoaledi is pleased that the Department of Health lost nothing and all the money that has been donated by the Global Fund is safe. 'It would have been a sad day if donor fund money was to disappear under our watch.' With the report now public, attention turns to the DBSA to fast-track the completion of the vital infrastructure. 'The remaining work of the DBSA will surely be expedited to conclude the project as expeditiously as possible to the benefit of the people of South Africa,' said the Minister. The Health Ministry says it remains committed to transparency, accountability, and delivering critical healthcare infrastructure without delay. IOL News