Nagpur: Petitioners in a PIL concerning the Ambazari flood disaster have challenged a report submitted by the Central Water and Power Research Station (CWPRS), Pune. They accused the report of legitimizing the unauthorized construction of Swami Vivekananda statue in the spill channel of Ambazari dam.
In a new affidavit filed before the Nagpur bench of Bombay high court, 91-year-old Ramgopal Bachuka and a group of senior citizens alleged that the CWPRS report was commissioned by Nagpur Municipal Corporation (NMC), which is under scrutiny for regulatory violations. The affidavit is part of a PIL seeking accountability for the flood on September 2023 that caused extensive damage.
"The CWPRS study cannot override legislative provisions, including the Irrigation Act and Wetland Rules, under which the statue's location is in a prohibited area," petitioners argued through counsel Tushar Mandlekar.
"The report is designed to justify an illegal structure rather than evaluate the flood dynamics accurately."
They objected to the minutes of the High Power Committee (HPC) meeting held on April 29, which accepted the CWPRS report and declined to consider relocating the statue. The HPC, they contended, failed to address key concerns, including prior affidavits by departments such as irrigation and urban development, which acknowledged the illegality of the site.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
It's Affordable and Actually Works
www.telidesk.com
Undo
The petitioners also noted that the CWPRS admitted to discrepancies in its data sets but proceeded to prepare simulations using a peak flood discharge of only 116.10 cumecs — the design standard for a 1-in-100-year flood. In contrast, the Ambazari dam is built to handle a discharge of 320 cumecs, or a 1-in-1,000-year event, according to the National Institute of Hydrology.
They alleged that the statue and associated amenities — including a pedestal, library, and public seating — obstruct the dam's tail channel, reducing water-carrying capacity and creating a bottleneck that contributed to flooding in the city.
Citing a 2024 affidavit from the principal secretary of the urban development department, the petitioners reiterated that the statue lies in a zone where development is restricted by govt resolutions issued on August 2, 2013 and March 8, 2018.
They also submitted reports from Hitbhav Engineers, and the Command Area Development Authority, which showed the tail channel's width had been reduced due to construction, aggravating flood risks at the confluence of the Nag and Pili rivers.
The petitioners have urged the court to reject the CWPRS report and direct authorities to restore the Nag River's natural flow by removing obstructions. The next hearing is scheduled for July 9.
BOX
Challenge To CWPRS Ambazari Flood Study
#Core Arguments:
CWPRS flood study termed a 'sham report'
Petitioners say it was influenced by NMC
HPC meeting failed to consider statutory violations
#Technical Disputes:
Dam discharge capacity: 320 cumecs
CWPRS simulation: 116 cumecs
Tail channel narrowed by statue platform, creating bottleneck
#Legal Grounds:
2013 & 2018 GRs prohibit any construction at site
Principal secretary's 2024 affidavit admits location is a 'prohibited area'
#Demand:
Court must reject report and restore Nag River's natural flow
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Indian Express
15 hours ago
- Indian Express
Involve students, their classmates and parents in assessment in Gujarat government schools: Expert panel
Soon, government schools will see a shift from a one-way evaluation to a system where students, along with their parents and classmates, will be involved in the assessment process of teaching and learning apart from teachers, as per the recommendations of a 360 degree assessment committee report placed before Chief Minister Bhupendra Patel recently. The assessment committee, formed on March 3 this year to overhaul the evaluation system of students, has also suggested the scrapping of the 'ekum kasauti' — the six-year-old unit test system, in the report, The Indian Express has learnt. The unit test, which was one of the most opposed education initiatives in state government schools, was on in nearly 40,000 primary and secondary government schools with a more informal, experiment-based, continuous evaluation. Along with the recommendation report, the committee has also prepared a format of Holistic Progress Card (HPC) for primary classes — foundational, preparatory and middle levels. 'The committee takes forward the National Education Policy 2020 that recommends that only teachers should not be evaluating the students, but all the stakeholders — students, their classmates and parents — should be involved in the self assessment process. The panel also suggested shifting of the weightage of evaluation from written exams to practical and written exams in equal proportion,' Jayendrasinh Jadav, educationist and Registrar at Gujarat Sahitya Akademi, Gandhinagar, who chairs the state-level committee, told The Indian Express. Three sub-committees were formed — for Balmandir, Class 1 and 2; for Classes 3 to 5; and for Classes 6 to 8 — that had prepared three Holistic Progress Cards. 'The Chief Minister and the officials were very positive towards the report and the presentation given by the committee. Though a couple of suggestions came from them as well, we are hopeful of a decision soon as the committee has almost completed the task that it was formed for, till there are any further directions from the state government,' Jadhav added. Education department officials stated that after the submission of the report, a decision on the implementation of recommendations will be announced. Further, the committee has said that teachers should be given freedom to decide when to conduct tests other than the total of four exams held in an academic year (two in each semester). 'We have suggested removal of the ekum kasauti, which requires uploading huge data of each child. This is mere data entry for which human hours (of teachers) get wasted. It is a futile exercise as we are not using this data. Everyone felt that this takes up most of the teaching hours,' Mitesh Bhatt, president of Rashtriya Shaikshik Mahasangh Gujarat, a teachers' body affiliated to the Rashtriya Swayamsevak Sangh (RSS), told this paper. Other than Jadhav, the committee comprises ten other members, including representatives from primary and secondary teachers' associations. Following repeated protests, representations and opposition to the ekum kasauti by teachers as well as educationists since it was launched in 2019-20, the Gujarat government formed the special committee to deliberate on the assessment of students other than weekly, fortnightly and monthly tests.


Hindustan Times
21 hours ago
- Hindustan Times
Centre didn't comply with NGT order on Great Nicobar project: Plea
The Union government has not complied with the National Green Tribunal's (NGT) April 3, 2023 order on revisiting the deficiencies in the environmental clearance granted to the Great Nicobar Holistic Development project, a petitioner challenging the green nod to the key project has claimed before NGT. The petitioner prayed that ecologically sensitive areas be excluded from project areas. (AFP) In a 39-page detailed submission made on July 24 by petitioner-environmentalist Ashish Kothari said the objective of this application is to seek the enforcement and implementation of the law. The petitioner highlighted that the three terms of reference for the NGT-appointed high-powered committee (HPC) were not met — specifically related to coral transplantation, environmental baseline data collection and review coastal regulation zone (CRZ) boundaries of the proposed port project. On April 3, 2023, NGT directed that clearance dated November 11, 2022 be revisited in the light of 'some unanswered deficiencies' pointed out by the appellants which need to be addressed. 'By way of instance, it is pointed out that out of 20,668 coral colonies, 16,150 are proposed to be translocated without any mention of threat to the remaining 4,518 coral colonies. It is pointed out that ICRZ Regulations prohibit destruction of corals. Further, data collected for impact assessment is only of one season as against requirement of three seasons. It is also shown that part of the project is in the CRZ IA area where Port is prohibited,' the NGT had said. HT had reported on April 7, 2023 that NGT had constituted a high-powered committee, headed by Union environment ministry secretary, to revisit the environmental clearance (EC) granted by the ministry to the Great Nicobar township and area development project. Experts, however, have questioned how a subordinate authority headed by the environment secretary revisit the green nod granted by its own ministry? In the submission to NGT, the petitioner has pointed out that several clauses of the Island Coastal Regulation Zone (ICRZ) Notification, 2019 and its annexure prohibit the destruction of corals. Annexure I to the notification prohibits destruction of corals, coral reefs and surrounding areas and allows coral transplantation activities only when necessary for regeneration after obtaining permission under the Wildlife (Protection) Act, 1972. Activities like dredging and discharge of ballast water are also prohibited in and around coral reefs. 'Even according to the MoEFCC, the HPC has only looked at the Zoological Survey of India's (ZSI) proposal to translocate coral colonies, and has agreed with the recommendation of ZSI. The mandate of the law, the fact that coral reefs are protected and that their translocation is not permitted by law etc. have not even been considered by the HPC,' the submission said. Importantly, the petitioner has pointed out that fringing coral reefs around the island have been marked clearly in the draft ICRZ coastal land use plans prepared under the 2019 notification but they are not there in the approved land use plans. 'Even according to the MoEFCC, the ZSI's report itself states that 16,150 coral colonies need to be translocated due to the port project. The ICRZ Notification, 2019 does not permit such transplantation to facilitate or clear the area for a port. Coral reefs and their associated biodiversity are extremely sensitive and cannot be moved around to suit the convenience of project proponents,' the submission added. It further claimed that the second aspect of TOR was also not met. 'The MoEFCC and the HPC have failed to see that the requirement of comprehensive EIA, i.e, an EIA based on three season data collection, is mandated under the ICRZ Notification, 2019 and the EIA guidance manual itself requires data collection of more than one season...' it said, adding that the survey of ecology and biology was conducted between December 14 and 22, 2020, and the survey of leatherbacks was conducted between February 12 and 18, 2021 and hence the season was not covered. The third ToR was to 'Review the boundaries of the port project with respect to ICRZ Notification, 2019.' The tribunal in its April 2023 verdict has observed that 'it is also shown that part of the project is in the CRZ IA area where Port is prohibited.' The 2019 notification lists mangroves, corals and coral reefs, biologically active mud flats, turtle nesting grounds, nesting grounds of birds as CRZ IA — ecologically sensitive areas. 'It is submitted that coral reefs, turtle nesting sites, megapode (bird) nesting grounds, mangroves, etc. do not and cannot magically disappear to suit the convenience of the project proponent. It is shocking that the HPC has relied only on a report of the NCSCM, the consultant of the project proponent, to come to the conclusion that no part of the project area falls under CRZ IA,' the submission said. The petitioner also prayed that ecologically sensitive areas be excluded from project areas. 'Unless this tribunal directs the exclusion of admitted CRZ IA areas such as coral reefs along the coast, turtle nesting grounds, megapode nesting grounds, biologically active mudflats etc. from the project area, they will be converted and destroyed,' it said. The matter was heard by NGT's eastern bench on July 24. People aware of the matter said additional solicitor general (ASG) Aishwarya Bhati submitted that the ministry did not violate any law and was aware of the sensitive nature of the island's environment and has ensured that sustainable development is achieved while keeping in mind the strategic requirements to ensure national security. The hearing was adjourned and the tribunal directed the MoEFCC to produce the revised layout which excludes all the CRZ-1A areas from the port, according to lawyers. The matter will be heard again on August 6. ASG Bhati did not respond to HT's request for a comment on whether the ministry will be making a submission on other concerns raised in the application. The Great Nicobar Holistic Development Project has four major components: an international container transshipment terminal (ICCT); an international airport; a power plant; and a township. The total cost is estimated at ₹81,800 crore. The Nicobar Islands fall in the Sundaland Biodiversity Hotspot and cover the western half of the Indonesian archipelago. Union environment minister Bhupender Yadav in August last year said that 'exemplary mitigation measures' have been incorporated to minimise the environmental impact of the project, 'keeping the strategic, national and defence interests' in mind. .


Time of India
a day ago
- Time of India
NMC admin to renovate, repair key offices before local body elections
Nashik: Nashik Municipal Corporation (NMC) administration has allocated Rs6 crore for the renovation of the offices belonging to the mayor, leader of the opposition and leader of the House. This decision comes as a new elected body is expected to take charge by the end of Dec 2025. The renovation plans also include the mayoral residential bungalow, "Ramayan". These upgrades are being undertaken in anticipation of the upcoming civic polls, which are likely to be held later this year in Nov or Dec. The civic administration has already issued three separate tenders for these renovation projects, collectively estimated at Rs6 crore. The previous general body of the NMC completed its five-year term in March 2022, and since then the civic body has been operating under the administrative governance owing to the delay of over three years in conducting civic elections. The ward delimitation programme has already started and the new ward formations are likely to be declared by the first week of Oct this year. An NMC official, while talking to TOI, said they are planning to renovate the offices of the mayor, deputy mayor, leader of the opposition, leader of the house and group leaders. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like Use an AI Writing Tool That Actually Understands Your Voice Grammarly Install Now Undo These offices are located at Rajiv Gandhi Bhavan — headquarters of the NMC. "We have already floated three different tenders, which include renovation and furniture work at the chamber of the leader of the house, leader of the opposition and group leader at Rajiv the civic headquarters at the cost of Rs4 crore," the official said. "Moreover, renovation and repairing work at the chambers of the mayor and deputy mayor office and Ramayan bungalow are to be undertaken at Rs1.74 crore," the official added. The last date for filing bids is Aug 8, while the tenders are to be opened on Aug 11. In the 2017 civic polls, BJP emerged victorious with a majority, winning 66 seats, followed by Shiv Sena with 35 seats. Both Congress and NCP got six seats each, while MNS got five and independents and RPI (A) got three and one seat, respectively. Get the latest lifestyle updates on Times of India, along with Friendship Day wishes , messages and quotes !