Green Bag roundabouts tied up in court
West Virginia Division of Highways District 4 Manager Earl Gaskins explained as much during a recent conversation with members of the Morgantown Monongalia Metropolitan Planning Organization.
"The Green Bag Road, as you guys can imagine, we're fighting with right of way on that. Right now we currently have eight parcels we have not acquired. We're moving for eminent domain on that, so we're waiting on the court system, " he said. "One of the things I'm seeing is we're overwhelming the court system. Everybody's busy, and by throwing these eminent domains in, we're overburdening the court system itself, but we're moving forward with that. Everything's looking good. Looks like we'll be able to get these knocked out here pretty soon and we'll get moving on the actual project."
Eminent domain is the power of the government to pay fair market value to take private property for public use — even if the property owner doesn't want to sell.
Conversation about Green Bag and its potential as a sort of Morgantown bypass for heavy trucks has been going on more than a decade. The discussion took on a different tone starting in 2018-2019 when it became clear the DOH was prescribing roundabouts to address backups at its intersections with Kingwood Pike and Mississippi Street intersections.
But roundabouts require land.
Notably, some of the land required is owned by the Hastings family and the site of a community garden. The family was outspoken in opposing the plan and ultimately pressured the DOH to conduct an environmental study for a project it initially said was exempt from such consideration.
In early 2022, the DOH issued its findings of no significant environmental impact.
Even so, a requirement to fund community gardens was attached to the project as a means of addressing the loss of the garden property. The MPO has recently distributed a total of up to $15, 000 to support the establishment of three community gardens.
The Green Bag Road project bid was awarded to Mountaineer Contractors on Dec. 6 for $18, 332, 804.40 in December.
The DOH previously said work on the project was likely to begin this spring and conclude in the fall of 2027.
The Dominion Post reached out to the DOH to ask if work would commence despite the right-of-way delays, but did not receive a response in time for this report.
Morgantown Industrial Park access bridge Much like Green Bag Road, Gaskins said the DOH is still working through right-of-way issues for the $59.7 million effort to span the Monongahela River to connect the Morgantown Industrial Park directly to U.S. 119 (Grafton Road).
"There are still two parcels we're fighting with. One is the railroad and the other one is a property we'll have to take through eminent domain, " he said.
According to Gaskings, Triton Construction has submitted a value engineering plan that would lower the cost to the contractor to build the project. Those plans are currently being reviewed by a third party.
"I don't want to be in a position where we can save money and we don't, and I also don't want to be in a position where this engineer and that engineer feel like they're just fighting back and forth, so we requested a third party to take a look at it."
As of the end of April, the DOH said steel should start being erected in early next year with completion forecasted for winter 2026.
Holland Avenue According to Gaskins, the DOH intends to award a contract to resurface Fairmont Road / Holland Avenue in the 2026 fiscal year, which begins July 1.
The project will run from a point near the Wes Mon Plaza to the Joseph Bartolo Memorial Bridge, more commonly known as the Westover Bridge.
Gaskins said the DOH is currently waiting on Westover's Holland Avenue stormwater and sewer line replacement project to wrap up. That project is expected to be completed in late June and will leave the road with an asphalt base.
Gaskins said the DOH will follow with a full-width overlay.
"We also have a project on the Joseph Bartolo Bridge that's being let as we speak. That will involve a deck overlay, drainage corrections, new expansion joints and all that, " he said. "So, you're going to get new pavement on 19 and the bridge will be redecked about that same time. So, hopefully you guys get some long-needed relief over there because I know you've been in pretty rough shape."
Other projects In addition to those mentioned above, Gaskins ran through a list of projects and provided their current anticipated completion dates.
— Every pothole in Monongalia County: Filled by the end of May. "You've got my word on that, " Gaskins said.
— Traffic lights at I-79 Exit 155: August 2025 — Walnut Street Streetscape: August 2025 — University Avenue / Collins Ferry Roundabout: August 15, 2026 — West Run Road between Stewartstown and Point Marion Road: May 10, 2027
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


Bloomberg
7 hours ago
- Bloomberg
Can This Bridge Ease the Troubled US-Canadian Relationship?
The new Gordie Howe International Bridge is less than two miles long, but it's been a long road to get there. Plans are on target for the opening this fall of the six-lane span crossing the Detroit River between Windsor, Ontario, and Detroit. The bridge, named for a Canadian hockey great who found fame on the ice for the Detroit Red Wings, promises to deliver 'unparalleled benefits for supply chains, industry and commercial users,' according to the Windsor-Detroit Bridge Authority, the Canadian crown corporation overseeing construction of the bridge.


Gizmodo
8 hours ago
- Gizmodo
Google's AI Master Plan in One Number
Alphabet, the parent company of Google, delivered a standout quarterly report on Wednesday, with robust growth across Search, YouTube, and Cloud. But buried beneath the strong revenues was a number that tells a much bigger story about the future of technology: $85 billion. That is Google's new budget for capital expenditures this year, a stunning $10 billion increase from its previous February's forecast. This colossal sum is being poured into the physical foundations of artificial intelligence: building more data centers, accelerating their construction, and filling them with tens of thousands of specialized servers and custom-designed chips. It is proof that the price of competing in the AI era is a full-scale infrastructure war, and Google is determined to win it by out-building everyone else. The reason for this massive spending is simple: demand for AI is growing at a nearly incomprehensible rate. CEO Sundar Pichai provided, in remarks recorded by the company, a metric to make this abstract concept tangible. In May, Google's systems processed 480 trillion 'tokens,' the basic units of data that AI models like Gemini use to read, write, and reason. Just a few months later, that number has more than doubled to 980 trillion monthly tokens. This exponential growth is a computational tidal wave, and it requires a physical response. Every AI-generated image, every summarized document, and every conversational response from the Gemini app consumes immense processing power. To meet this demand, Google is in a constant race to build the digital factories where this work happens. Chief Financial Officer Anat Ashkenazi explained, during the call with analysts, the spending hike is driven by 'additional investment in servers, the timing of delivery of servers, and an acceleration in the pace of data center construction, primarily to meet cloud customer demand.' What sets Google apart in this arms race is its strategy of owning the entire technology pipeline, what Pichai calls a 'differentiated, full-stack approach to AI.' This means Google not only designs the world's most advanced AI models but also controls the physical infrastructure they run on. This includes its global network of AI-optimized data centers and, crucially, its own custom-designed Tensor Processing Units (TPUs). These are specialized chips built for the exact kind of mathematics that powers AI, giving Google a significant advantage in both performance and cost over competitors who must rely on more general-purpose chips from third parties. This control over the 'full stack' creates a powerful competitive moat. While other companies, even major AI labs, must rent their computing power, Google owns the factory. This is why, as Pichai noted, 'nearly all gen AI unicorns use Google Cloud,' and why advanced research labs are specifically choosing Google's TPUs to train their own models. OpenAI recently said that it expected to use Google's cloud infrastructure for its popular ChatGPT service. OpenAI Quietly Turns to Google to Stay Online The $85 billion bet is about more than keeping up with demand. It is a long-term strategy to build and control the foundational layer of the next era of computing. By investing so heavily in the digital equivalent of roads, power grids, and factories, Google aims to ensure its dominance for the next decade. Any company that wants to build a significant AI application will, in some way, likely have to run it on infrastructure built by Google. Even with this massive spending, the company is still racing to keep up. Ashkenazi delivered a crucial warning that Google expects to 'remain in a tight demand-supply environment going into 2026.' This reveals the sheer intensity of the AI arms race. The demand for AI compute is so ferocious that even a company spending $85 billion in a single year is struggling to build fast enough. Google's message is clear: The AI revolution will not be built on code alone. It will be built on a foundation of silicon, fiber optics, and concrete. The $10 billion spending increase is the non-negotiable price of victory, a down payment on a future where Google doesn't just lead in artificial intelligence, but owns the planet it runs on.


Bloomberg
10 hours ago
- Bloomberg
Czech Bank CEO Sees More Investment If Billionaire Wins Election
The potential return of billionaire Andrej Babis to power after October's parliamentary election would bring an increase in infrastructure investments, according to a Czech banking executive. If Babis's party were to win the vote, as polls currently suggest, Czechs will see that one of his key objectives will be to spend more on infrastructure, Moneta Money Bank AS Chief Executive Officer Tomas Spurny said on Thursday. It's an area where the country has 'significant room' for growth, he added.