City loses court case against Cell C over stadium damage

City loses court case against Cell C over stadium damage

IOL News13-06-2025
Cape Town stadium.
Image: City of Cape Town
THE City has lost its court bid to claim damages against Cell C over damage to the Cape Town stadium.
The Western Cape High Court ruled that the debt had prescribed, and the claim was dismissed with costs.
According to court papers, the issue dates back to 2015 when the City gave Cell C permission to access the stadium to install infrastructure for its customers.
Cell C had contracted Huawei to do the installation work.
'On November 18, 2015, the (City) discovered extensive damage to the external façade of the stadium which was caused by a metal panel which had dislodged from gridline 50 on level 6 of the stadium and which fell on or through the façade, damaging the same.
"At all material times it was (Cell C's) duty to ensure that the installation was done without any harm or damage to the stadium and inasmuch as the damage was caused by (Huawei), alternatively, the third, alternatively the fourth defendant's action, it remained the duty of (Cell C) to ensure that no damage was done to the stadium and it could not rid itself of this duty by appointing a contractor,' court papers read.
Video Player is loading.
Play Video
Play
Unmute
Current Time
0:00
/
Duration
-:-
Loaded :
0%
Stream Type LIVE
Seek to live, currently behind live
LIVE
Remaining Time
-
0:00
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
Text Color White Black Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan
Transparency Transparent Semi-Transparent Opaque
Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps
Reset
restore all settings to the default values Done
Close Modal Dialog
End of dialog window.
Advertisement
Next
Stay
Close ✕
Ad loading
The City's main claim was against Cell C with an alternative claim against Huawei and the other sub-contractors separately, in the event that the court found that they were independent contractors and that Cell C could not be held liable for any of their actions.
However, both Cell C and Huawei invoked a special plea of prescription.
They argued that the cause of action arose on November 18, 2015 and that the summons instituting the proceedings was served on them after the three year prescription period.
'The (City's) claim would prescribe within a period of three years as it falls within the ambit of section 11(d) of the Prescription Act. In his opening statement counsel for (Cell C) submitted that the (City) sought to impose strict liability on it in terms of its pleaded case. This rendered the actual identity of the defendant / entity who caused the damage irrelevant. Furthermore, Cell C submitted that as the (City) discovered the loss on November 18, 2015 and served its summons on November 21, 2018, (the City's) claim against it had prescribed.'
Lawyers for Huawei argued that there were no grounds on which the City could succeed. An ICS service engineer for Huawei testified and that he was responsible for the network provision.
The engineer compiled a report on the day of the incident at the stadium. It was recorded that on November 18, 2015 the stadium management stated that the damage was caused by Huawei's contractors as they worked on location. The report contained Huawei's denial that they were responsible for the damage and concluded that there was no conclusive proof in respect of who was responsible for the damage.
A City employee testified that while he was aware of a theory that a cherrypicker from another company could have caused the damage, 'no one placed any credibility in the theory'.
He said that there was one of four entities (Cell C, Huawei and the other subcontractors) which could be liable for the damage and that he held a meeting with representatives of all four entities on November 18, 2015.
However, according to court papers, the employee never asked which contractor replaced the panel and who was responsible for supervising the work on level 6.
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Four clubs that could sell their elite status to Comitis after Cape Town City's relegation
Four clubs that could sell their elite status to Comitis after Cape Town City's relegation

IOL News

timea day ago

  • IOL News

Four clubs that could sell their elite status to Comitis after Cape Town City's relegation

TS Galaxy owner Tim Sukazi and Cape Town City boss John Comitis have been good friends for some time. Now that Galaxy have been slapped with a hefty Fifa penalty, it may be a good time to sell. Photo: BackpagePix Cape Town City owner John Comitis, one of the wealthiest club bosses in the PSL, is reportedly actively exploring avenues to purchase the top-flight status of another club. This comes in the wake of City's relegation to the Motsepe Foundation Championship, following a disappointing play-off campaign. Born in Kinshasa, DRC, Comitis is a former professional player who turned out for Wits University, Jomo Cosmos, Hellenic, Cape Town Spurs, Vasco da Gama, and Korinthos FC in Greece. During a recent radio interview, Comitis reflected on the daunting challenge of fighting for promotion in the second tier. Said Comitis: 'The shortest route (buying a franchise) is the best route.' The sentiment echoes Comitis' initial entry into the PSL, when he acquired the status of Mpumalanga Black Aces and subsequently founded Cape Town City in July 2015. He has acknowledged the financial complexities involved and the potential backlash from sponsors, many of whom are hesitant to continue their backing while the club operates outside the top division. City currently have several sponsors on board, but Comitis confirmed they are likely to withdraw if the club competes in the second tier. Questions now swirl around which clubs might be willing to part with their top-flight status — a decision that would come with serious financial implications. While nothing has been confirmed, four clubs have emerged as potential candidates for Comitis' pursuit:

Tshwane Mayor vows to enforce High Court ruling on Edwin Sodi-linked tender
Tshwane Mayor vows to enforce High Court ruling on Edwin Sodi-linked tender

IOL News

time2 days ago

  • IOL News

Tshwane Mayor vows to enforce High Court ruling on Edwin Sodi-linked tender

Tshwane Mayor Nasiphi Moya has assured residents that her administration will take decisive action to implement the High Court ruling, requiring companies linked to businessman Edwin Sodi to repay the profits from a 2019 tender valued at almost R300 million for the Rooiwal Waste Water Treatment Plant upgrade. Image: Oupa Mokoena / Independent Newspapers Tshwane Executive Mayor Nasiphi Moya has assured residents that her administration will take decisive action to enforce a Gauteng High Court ruling requiring companies linked to businessman Edwin Sodi to repay profits from a nearly R300 million 2019 tender for the Rooiwal Waste Water Treatment Plant upgrade. The contract awarded to the consortium, comprising Blackhead Consulting, NJR Projects, and CMS Water Engineering, linked to Edwin Sodi, was terminated in August 2022 due to significant issues and delays with the quality of work, resulting from persistent stalling of Phase 1 of the project. The Rooiwal upgrade project aimed to enhance the wastewater treatment plant's capacity to process the high volume of wastewater it receives. For over a decade, the issue of contaminated water supplied to Hammanskraal residents has been linked to the Rooiwal plant's insufficient capacity to properly purify wastewater, resulting in sludge being discharged into the Apies River. Video Player is loading. Play Video Play Unmute Current Time 0:00 / Duration -:- Loaded : 0% Stream Type LIVE Seek to live, currently behind live LIVE Remaining Time - 0:00 This is a modal window. Beginning of dialog window. Escape will cancel and close the window. Text Color White Black Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Background Color Black White Red Green Blue Yellow Magenta Cyan Transparency Opaque Semi-Transparent Transparent Window Color Black White Red Green Blue Yellow Magenta Cyan Transparency Transparent Semi-Transparent Opaque Font Size 50% 75% 100% 125% 150% 175% 200% 300% 400% Text Edge Style None Raised Depressed Uniform Dropshadow Font Family Proportional Sans-Serif Monospace Sans-Serif Proportional Serif Monospace Serif Casual Script Small Caps Reset restore all settings to the default values Done Close Modal Dialog End of dialog window. Advertisement Next Stay Close ✕ Ad loading The Apies River in turn supplied water to Temba water treatment plant, used for purifying water for the Hammanskraal residents. The high court ordered the companies to repay the City profits made from the contract. According to the court ruling, the High Court will determine the exact amount of profit to be repaid to the City after the consortium submits its expenses within 60 days. Moya said if the companies fail to submit their expenses as ordered by the court, the City will appoint an independent contractor to determine the expenses and calculate the profits made from the tender. 'The court's decision affirms what we have long maintained that contracts awarded through unethical and irregular processes undermine service delivery, compromise governance, and erode public trust. We assure the residents of Tshwane that this administration will act decisively to give full force and effect to the order,' she said. Moya said work to complete the upgrades to the Rooiwal Waste Water Treatment Plant have progressed successfully with Phase 1B underway after work on Phase 1A was completed ahead of schedule. Last week, Tshwane's Section 79 Utility Services committee expressed satisfaction with the Department of Utility Services' progress in refurbishing the treatment plant, saying the project is currently in Phase 1B, which commenced in April 2025, focusing on civil works. DA caucus leader Cilliers Brink welcomed the court ruling, saying it validates the DA-led coalition's decision to initiate litigation and attempt to blacklist the Sodi consortium. He said the consortium lacked the necessary expertise for the project and abandoned the site prior to the investigation. He called on the City to make public the progress in completing the blacklisting process. City Manager Johann Mettler previously announced that the metro had started the process of blacklisting the implicated companies from conducting business with the government by applying to the National Treasury. Brink said:'The tender for the upgrade of the Rooiwal Waste Water Treatment Plant was awarded to the Sodi consortium in 2020. In 2022 a forensic investigation found that the consortium should have been disqualified from the even bidding.'

Over 400 new bays for hawkers approved in Cape Town CBD
Over 400 new bays for hawkers approved in Cape Town CBD

The South African

time3 days ago

  • The South African

Over 400 new bays for hawkers approved in Cape Town CBD

City Council has approved four major informal trading plans around Cape Town, unlocking a total of nearly 800 new trading opportunities. As many as 416 trading bays have been proposed for Cape Town's Grand Parade alone. This is already one of Cape Town's busiest and most contested trading hubs. Other areas set to benefit from the move include Mamre and Pella near Atlantis, Elsies River, and Gatesville. Together, these plans aim to create more inclusive, better-regulated, and economically viable trading spaces for hundreds of hawkers and the communities they serve. 'These plans are not just about regulation – they're about practical improvements that support local traders and stimulate economic activity,' said Alderman James Vos. 'We've pushed to get them approved because I've seen first-hand the positive impact they've had in areas where similar interventions have been implemented.' According to a statement released by the City, the new initiative aims to improve the infrastructure of trading bays and the surrounding spaces. The City also plans to give permits to previously unpermitted hawkers, giving them access to City support services. This in turn would help improve compliance in line with the City's Informal Trading by-law. The breakdown of new trading opportunities is as follows: Grand Parade, Cape Town CBD: 416 bays Gatesville: 265 bays (including 116 new opportunities) Elsies River: 60 bays Mamre and Pella: 42 bays The above allocations are set to significantly expand economic opportunities for hawkers and the entire value chain. Vos also emphasised the importance of consultation in shaping the plans. 'I really enjoy engaging with traders and hearing directly from them about what's needed,' he added. 'These plans are shaped by such conversations and are designed to create cleaner, safer, and more functional trading spaces.' Let us know by leaving a comment below, or send a WhatsApp to 060 011 021 1. Subscribe to The South African website's newsletters and follow us on WhatsApp, Facebook, X and Bluesky for the latest news.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store