RM250 million water treatment plant to be built at Mengkuang dam for consumers in SPT
He said the proposed project, which will be about 550 metres from the Expanded Mengkuang Dam (EMD), when completed in November next year, is capable of supplying a maximum of 114 million litres per day (MLD) of treated water to consumers, particularly in the Seberang Perai Tengah (SPT) district.
The Taman Mengkuang WTP project, expected to take 18 months to complete, will draw daily water supply from the EMD, which is the largest dam in the state, he said.
'So far, the EMD has served as a strategic water storage dam, releasing water only during emergencies when the Sungai Dua Water Treatment Plant (WTP) is unable to abstract sufficient water from Sungai Muda.
'However, starting November 2026, EMD will transition into a dual-purpose dam. Once fully operational, it will release raw water daily to support the Taman Mengkuang WTP, while continuing to serve as an emergency backup source for the Sungai Dua WTP under abnormal conditions,' he added.
Chow, who is PBAPP chairman, told reporters this after opening the groundbreaking ceremony for the Taman Mengkuang WTP Project here today.
He said the construction of the new WTP was among the proactive measures taken by the state government to address the growing water demand, as Penang's water consumption has risen from 813 million litres per day (JLH) in 2014 to 870 JLH in 2024, with projections indicating it will further increase to 1,103 JLH by 2030.
Meanwhile, PBAPP chief executive officer Datuk K. Pathmanathan said the project includes the construction of a 114-JLH water treatment module, a backwash pump house, a chemical dosing building and a treated water tank.
In addition, he said, it also involves the construction of a sludge treatment building, a cleaning pump and a chemical waste storage pond, a storage pond and an administration building equipped with a supervisory control and data acquisition (SCADA) system.
'This contract also includes the installation of a 1,200-millimetre (mm) diameter raw water discharge pipe from the dam and a 900mm-diametre treated water production pipe for connection to the existing treated water supply line.
'It also involves all civil, structural, mechanical and electrical works,' he said.
According to Pathmanathan, currently, most of the treated water supply at SPT is drawn from the Sungai Dua WWTP in Seberang Perai Utara (SPU), but this dependence is expected to decrease when the Taman Mengkuang WWTP begins operating.
He said the new LRA would not only strengthen the water supply in SPT but also provide indirect benefits to consumers in SPU and South Seberang Perai (SPS).
He said the Taman Mengkuang LRA is the third project under the Water Contingency Plan 2030 (WCP 2030), and there are five more projects under the plan that need to be completed before 2030.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Sun
a day ago
- The Sun
Penang launches Silicon Research and Incubation Space to drive IC design industry
GEORGE TOWN: Penang's mission to lead Malaysia's integrated circuit (IC) design landscape received a boost with the launch of the Silicon Research and Incubation Space, a high-innovation facility under the Penang Silicon Design @5km+ (PSD@5km+) initiative. Located at GBS Tech Space in the Bayan Lepas Industrial Park, the 36,000-square-foot purpose-built space marks the beginning of a new era for local IC design, poised to meet the challenges of the global market. Chief Minister Chow Kon Yeow said the facility is now home to local IC design companies and technology partners, creating a collaborative platform that brings together the experience, expertise, and vision of local entrepreneurs, many of whom previously served in multinational corporations (MNCs). He said the facility is envisioned as a one-stop centre designed to cultivate a vibrant community of next-generation artificial intelligence-driven IC design thinkers, engineers and entrepreneurs. 'It provides access to high-specification server environments, cutting-edge lab facilities and industry-standard electronic design automation tools and equipment, which are critical enablers for IC design and development. 'The space is also complemented by an integrated suite of technical consultations, expert mentorships and collaborative development programmes, aimed at accelerating innovation and product readiness,' he told a press conference after the launching ceremony at the GBS Tech Space, here today. Chow noted that today's launch reaffirms the state's commitment to aligning with the National Semiconductor Strategy, and over 45 companies, both local and MNCs, are currently operating in Penang, making it Malaysia's largest IC design cluster. Elaborating further, he said the facility is one of three key components under the PSD@5KM+ initiative, the other two being the Chip Design Academy, which is to be launched next week, and the IC Design Digital Park in Bayan Lepas, scheduled for completion this August. The PSD@5KM+ initiative was launched by Prime Minister Datuk Seri Anwar Ibrahim in December last year, with support from RM50 million in federal government funding and RM60 million from the state government. Chow emphasised that the state's vision, 'Made by Malaysia, designed and developed in Penang', is becoming a reality as locally designed chips begin to meet global standards and enter international markets. He said that one of the recent achievements is the development of two advanced chip technology solutions, namely HBM3E and network-on-chip by SkyeChip. 'We are proud that local companies are now not just 'Made in Malaysia', but are producing chips that are truly 'Made by Malaysia', reinforcing Penang's position as the Silicon Valley of the East,' he added.


Malaysian Reserve
a day ago
- Malaysian Reserve
Chow: Penang waiting for notice to proceed to start physical construction of LRT
GEORGE TOWN — The Penang government is still waiting for the official notice to proceed (NTP) from the Transport Ministry and Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) so that the Mutiara Line Light Rail Transit (LRT) physical construction can begin. Penang chief minister Chow Kon Yeow said the notice was required to allow SRS Consortium Sdn Bhd (SRS), as the main public work contractor for Package 1 of the project to start according to the plan and schedule. 'Some initial work has been done at the project site, including soil study, land acquisition and compensation negotiations with owners, but the official notice is important to allow physical construction work completely,' he told reporters after officiating the 2025 Penang Transport Day at Komtar today, in the presence of state Infrastructure, Transport and Digital Committee chairman Zairil Khir Johari. He added that the state government has done its duty when it handed over its role in the project to MRT Corp and released SRS Konsortium as the party that had requested the LRT implementation previously. 'The state government's link with SRS is now in the context of the Penang Transport Master Plan, but the LRT project has been taken over by MRT Corp. The main duty is now with the federal government to issue the notice,' he said. Chow also said that the contractor has to ensure that the road area taken up is replaced by expanding the road on the side by maintaining the number of existing lanes to avoid traffic congestion that occurred during the LRT construction in Kuala Lumpur. The state government does not plan to impose any congestion charge as the priority was to ensure that the project and traffic management during the construction period run smoothly, he added. — BERNAMA


The Sun
a day ago
- The Sun
Penang waiting for notice to proceed to start physical construction of LRT
GEORGE TOWN: The Penang government is still waiting for the official notice to proceed (NTP) from the Transport Ministry and Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) so that the Mutiara Line Light Rail Transit (LRT) physical construction can begin. Penang chief minister Chow Kon Yeow said the notice was required to allow SRS Consortium Sdn Bhd (SRS), as the main public work contractor for Package 1 of the project to start according to the plan and schedule. 'Some initial work has been done at the project site, including soil study, land acquisition and compensation negotiations with owners, but the official notice is important to allow physical construction work completely,' he told reporters after officiating the 2025 Penang Transport Day at Komtar today, in the presence of state Infrastructure, Transport and Digital Committee chairman Zairil Khir Johari. He added that the state government has done its duty when it handed over its role in the project to MRT Corp and released SRS Konsortium as the party that had requested the LRT implementation previously. 'The state government's link with SRS is now in the context of the Penang Transport Master Plan, but the LRT project has been taken over by MRT Corp. The main duty is now with the federal government to issue the notice,' he said. Chow also said that the contractor has to ensure that the road area taken up is replaced by expanding the road on the side by maintaining the number of existing lanes to avoid traffic congestion that occurred during the LRT construction in Kuala Lumpur. The state government does not plan to impose any congestion charge as the priority was to ensure that the project and traffic management during the construction period run smoothly, he added.