logo
#

Latest news with #SpencerBridgeEngineering

Menai Suspension Bridge update on work planned in phase two of mammoth makeover
Menai Suspension Bridge update on work planned in phase two of mammoth makeover

North Wales Live

time20-07-2025

  • Automotive
  • North Wales Live

Menai Suspension Bridge update on work planned in phase two of mammoth makeover

The team behind the massive revamp of the Menai Suspension Bridge have explained the work that will take place in the coming months. On October 1, 2022, the bridge linking Anglesey and Gwynedd was shut abruptly following the discovery of structural issues. Phase one works to replace the bridge hangers began on September 4, 2023, and were completed in October 2024. Welsh Government then delayed the start of Phase two - with that work starting in March 2025, with a planned completion by the end of the year. This was then put back to spring 2026 which means roadworks and traffic lights will remain in place for months longer, with just one lane open. It was a decision attacked by Plaid MS Rhun ap Iorwerth. UK Highways A55 Ltd, and primary contractor Spencer Bridge Engineering, this week put out information about the work that is taking place. They said the completion of this phase will help safeguard the Menai Suspension Bridge, a Grade I listed Georgian structure, for generations to come. This follows the success of Phase One which replaced 168 hangers using custom technology. The latest phase of works includes essential maintenance to the bridge's corbels, land saddles, parapets and underdeck as part of a new work programme. Currently, all of the bridge's hangers are receiving new coats of paint and UK Highways A55 Ltd is finalising all the necessary certifications and approvals for each of the Phase Two elements. This new work programme has been optimised using new data and experience from Phase One, particularly the challenging weather conditions of the Menai Strait. The new project will see Spencer Bridge Engineering's teams carry out repair works on 15 of the bridge's corbels - concrete beams which support the footway on the approach spans. During Phase One the team were able to repair 45 of the 60 corbels using rope access, but the remaining 15 require intrusive works to be carried out on site. The team will also carry out repair and painting of the parapets, which run along the entire length of the bridge, as well as the load checking and re-stressing of the land saddles, which anchor the cables of the bridge to the ground on the Anglesey side of the bridge. The Spencer Bridge Engineering team will deploy its innovative new modular moving access system for the first time, during the underdeck painting stage of the project. Named AeroTruss, this is an innovative access system which has been developed and designed by Spencer Bridge Engineering's expert in-house team to address common issues associated with other temporary access systems currently available in the market. They said the AeroTruss system will ensure the team can safely access the underdeck of the bridge, while minimising load effects into the bridge structure, due to its aerodynamic properties. Luke Fisher, Spencer's Bridges Director, said: 'We are delighted to be continuing our successful partnership with UK Highways A55 Ltd to restore this iconic bridge and ensure it can remain in use for decades to come. This project is particularly exciting for us as it's the first time we are using our new AeroTruss system, which has been in development for over three years. "With over 25 years' experience in the bridges sector, we've become familiar with some of the common issues faced while working on high-level structures, so we've developed AeroTruss to address these issues and ensure we can provide clients with the most efficient, high-quality service, while protecting the historic structures we're working on.' As part of their commitment to deliver for Anglesey and north Wales, UK Highways A55 Ltd and Spencer Bridge Engineering said they continue to engage and appoint local contractors to support the work programmes where possible including all of the hanger painting technicians being recruited from the local area.

Major works to be carried out on three Scottish bridges
Major works to be carried out on three Scottish bridges

The National

time06-05-2025

  • Automotive
  • The National

Major works to be carried out on three Scottish bridges

Engineering works on Forth Road Bridge, Tay Bridge and Kessock Bridge will take place during 2025 and 2026. Specialist contractor Spencer Bridge Engineering was appointed to undertake the works, having worked on similar infrastructure projects for the last 30 years. Forth Road Bridge The firm is set to replace the lateral thrust bearings on the Forth Road Bridge, which are from the bridge's original construction in the early 1960s and have reached the end of their serviceable life. The project will begin this year with engineers installing temporary steelwork to enable the replacement, with replacement work taking place next year during a period of "favourable weather". READ MORE: Police officer found guilty of sexually assaulting two colleagues The contractor will also replace two underdeck gantries on Tay Road Bridge, which connects Dundee to Newport-on-Tay. Tay Road Bridge A team will replace the gantries, which have been in place since the 1980s, to allow future maintenance works to be carried out more efficiently. The third project is at Kessock Bridge, which crosses the Beauly Firth at Inverness. Spencer Bridge Engineering has been appointed to carry out steelwork modifications on the pylons on the bridge. Kessock Bridge (Image: Dave Conner) Once completed, the works will allow improved access and will create a rescue system to improve the safety of workers in the event of an emergency. Glen Smithson, operations director at Spencer Bridge Engineering, said: 'Having the ability to provide turnkey solutions, delivering both the design and installation works, enables us to have tight control of each element of the project and ensure we are delivering the highest quality works in the most efficient way. READ MORE: Nicola Sturgeon breaks silence on Supreme Court gender ruling 'Our ethos of having strong collaboration with our clients ensures our projects are more closely tailored to each client's individual needs and specifications. 'Our teams are adept at working in remote, exposed locations, with difficult logistics, which is another factor which makes us so well equipped to work on so many Scottish infrastructure projects.'

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store