Mysuru district achieves over 84% progress in rural drinking water supply under Jal Jeevan Mission

Mysuru district achieves over 84% progress in rural drinking water supply under Jal Jeevan Mission

Time of India2 days ago
Mysuru: Mysuru district achieved 83.9% progress under the Jal Jeevan Mission, providing safe drinking water to 4.5 lakh rural households. The zilla panchayat's rural water supply department made significant strides toward the target of 4.79 lakh households.
Jal Jeevan Mission aims to supply safe and adequate drinking water through individual household tap connections by 2028 to all households in the district. The scheme also included measures for water source sustainability, like recharge, reuse, grey water management, water conservation, rainwater harvesting, and the construction of overhead tanks.
Under the scheme, ZP targeted 618 villages in 291 gram panchayats by implementing 13 development works at an estimated cost of Rs 1,293.66 crore.
ZP spent Rs 896.9 crore, accounting for 69.3% of the total allocation, and achieved 83.9% physical progress by covering 4.45 lakh households by the end of June. Approximately 65.9 MLD of water was planned for households under the scheme.
The state and Union governments contributed equally with 37.5% of the funds, while ZP funded 15% under the 15th Finance Commission grants and another 10% was collected from beneficiaries for tap water connections.
Priority was given to villages under the Multi-Village Drinking Water scheme, as they already had water sources supplied. Officials said that ZP provided piped drinking water connections by undertaking 1,580 man days of work against the planned 1,909 man days.
ZP rural drinking water supply executive engineer Ranjeeth Kumar said that ZP had provided piped water connections to 4.45 lakh households and would cover the remaining 26,000 households by 2028.
Speaking to ZP CEO Ukesh Kumar, he gave directions to all implementing officers and agencies undertaking the Jal Jeevan Mission project to maintain transparency and avoid damaging roads, existing drinking water, sewer, and drainage lines in all villages. He also conducted on-site inspections in various villages to address complaints.
Once households received tap water connections, local gram panchayats would be empowered to supervise, install water meters for these connections, and collect the necessary taxes from villagers.
"As many roads and drainage lines were damaged by workers involved in laying piped water connections under the JJM mission in several villages, officials must repair and solve such complaints on priority besides completing works to ensure safe drinking water to villagers," said Benakanahalli GP member HM Sambhram.
Taluk-wise progress
- H D Kote taluk: 60,000 households provided tap connections against a target of 71,000
- Hunsur taluk: 61,000 households against 62,000 target
- K R Nagar taluk: 59,007 households against 60,000 target
- Mysuru taluk: 68,000 households against 72,000 target
- Nanjangud taluk: 79,000 households against 81,000 target
- Periyapatna taluk: 57,000 households against 60,000 target
- T Narasipura taluk: 61,000 households against 64,000 target
Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

After Shimla and Manali this road in Himachal becomes a new tourist spot: Watch viral video
After Shimla and Manali this road in Himachal becomes a new tourist spot: Watch viral video

Time of India

time3 hours ago

  • Time of India

After Shimla and Manali this road in Himachal becomes a new tourist spot: Watch viral video

Something that can't even be imagined in fiction has happened in Himachal Pradesh, where electricity poles have been installed right in the middle of a newly constructed road, raising serious questions about infrastructure planning and inter-departmental coordination. The incident gained widespread attention after a video was shared by X user @raavan_india. In the video, the user draws a satirical comparison between Himachal Pradesh and Bihar, where trees were reportedly planted in the middle of roads. 'While Bihar plants trees on roads, Himachal has taken it a step further by installing electricity poles,' he says, pointing out the illogical placement. Viral video turns road into a local attraction The man further comments that the road has unintentionally become a tourist spot. 'This is very entertaining, this place has become a tourist place. People visit here to see this wonder,' he remarks in the video. He adds, with irony, that the poles may be strategically placed to test the reflexes and skills of drivers navigating the route. — raavan_india (@raavan_india) Live Events Incident triggers online reactions The video prompted a wave of online reactions, with one viewer questioning, 'Were poles erected first or the road was made first?' As reported in the video and responses, the incident has sparked a wider conversation about the need for better coordination between government departments involved in infrastructure development. In Bihar, trees planted in the middle of the road A similar case in Bihar's Jehanabad district, around 50 km from Patna, has also come under public criticism. A 7.48-kilometre stretch of the Patna–Gaya main road, built at a cost of Rs 100 crore, features several trees standing awkwardly and dangerously in the middle of the widened road. According to inputs from agencies, the trees were not removed during construction due to a dispute between the district administration and the forest department. While permission was sought to cut down the trees, it was denied after the forest department demanded compensation for 14 hectares of forest land—something the administration failed to provide. As a result, the road was constructed around the trees. — souravreporter2 (@souravreporter2) The trees are not even aligned in a straight row, and their scattered placement has turned the road into a safety hazard. Locals say the stretch has already seen multiple accidents, particularly at night or when vehicles are travelling at high speeds. 'Anyone driving at night or at high speed can easily crash into these trees,' said a resident. Despite rising concerns, no corrective action has been taken so far. Many residents feel the project has not only wasted public funds but also endangered lives due to the lack of coordination and planning. Both incidents, though separated by geography, underscore the need for tighter oversight and communication between agencies involved in infrastructure development.

Arunachal APSSB CSL notification 2025 out for 461 posts; apply from August 1
Arunachal APSSB CSL notification 2025 out for 461 posts; apply from August 1

Scroll.in

time5 hours ago

  • Scroll.in

Arunachal APSSB CSL notification 2025 out for 461 posts; apply from August 1

The Arunachal Pradesh Staff Selection Board (APSSB) has released the official notification for the Combined Secondary Level Examination 2025. Eligible candidates can apply for the posts at from August 1 to 25, 2025. The written exam is tentatively scheduled to be conducted on October 26, 2025. The PET/ PST will be conducted on November 18, 2025. The recruitment drive aims to fill 461 vacancies. Applicants can check the eligibility criteria, age limit, pay scale, and other details available in the notification below: Here's the official notification. Application Fee A non-refundable fee of Rs 150 for APST candidates and Rs 200 for unreserved candidates (to be paid online only). Persons with Disabilities (PwD) are exempted from paying the fees.

Incomplete link road plagues Ameenpur commuters
Incomplete link road plagues Ameenpur commuters

New Indian Express

time7 hours ago

  • New Indian Express

Incomplete link road plagues Ameenpur commuters

HYDERABAD: Residents of Ameenpur, including Chakrapuri, Lala Bhai Colony and Sunway Opus Layout, continue to suffer poor road connectivity despite over RS 10 crore sanctioned for a key link road connecting Miyapur and Bachupally. The project remains incomplete due to legal hurdles, disputes over private land, and poor coordination among authorities, say locals While the Ameenpur municipal authorities gave developed nearly 80% of the 30-foot-wide road, critical gaps of 100–150 metres near Chakrapuri and Golden Meraki remain unresolved. 'This stretch could ease traffic on the Miyapur main road and serve over a lakh daily commuters, including schoolchildren and officegoers,' civic activist RK Yadav told TNIE. 'Some segments are fully built with BT layers, but key patches through private lands are blocked or damaged, with security guards posted.' Layouts like Sai Ambica to Miyapur fall under municipal jurisdiction but remain inaccessible due to broken or missing road links. Commuters are forced to take longer, unsafe detours. 'Every morning, we waste 20 extra minutes navigating muddy lanes and potholes,' said Vignesh, a daily commuter. 'During rains, auto drivers avoid the area or charge extra.' Another resident, Kiran Kumar, said school buses and trolley autos frequently get stuck. 'It's a safety hazard. Children and elderly residents are most affected,' he said. Yadav said revised proposals have been submitted to resolve land and survey issues through a new tender process, but progress remains slow. Legal disputes and land classification issues continue to delay the road's completion. 'Thousands rely on these informal roads to reach Miyapur and Bachupally, but without official recognition or maintenance, they remain potholed and unsafe,' Yadav added. Residents have urged the municipal authorities to expedite land acquisition, mediate with landowners and complete the pending patches to make the road fully functional.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store