The completion of India's longest rail tunnel between Devprayag and Janasu in Uttarakhand faced significant challenges, including moments when it seemed the tunnel might collapse and jeopardise the whole project, Larsen & Toubro Limited (L&T) said on Saturday. "The tunnel boring machine (TBM) named 'Shakti' was about five km inside the tunnel when it encountered a gush of water from all directions at the rate of around 1,500 litres per minute," Rakesh Arora, Project Director of the tunnel, told PTI.
#Pahalgam Terrorist Attack
India pulled the plug on IWT when Pakistanis are fighting over water
What makes this India-Pakistan standoff more dangerous than past ones
The problem of Pakistan couldn't have come at a worse time for D-St
"Besides the TBM operator, there were 200 people inside the tunnel at that time. It was one of the toughest moments when the tunnel was at risk of flooding or collapsing. However, we took corrective measures immediately," he said.
Arora said the situation did not improve for around a month. His team struggled to overcome it by using a combination of chemical as well as cement grouting to stabilise the rings and surrounding rock, consequent to which, the water flow started reducing and the engineers could stabilise the interiors successfully, he added.
by Taboola
by Taboola
Sponsored Links
Sponsored Links
Promoted Links
Promoted Links
You May Like
Nipanya: The price (& size) of these hearing aids might surprise you
Hear.com
Learn More
Undo
"Besides, there were occasions when huge pressure from the surrounding soft rock posed a serious risk to the tunnel's progress, which was successfully handled by speeding up the excavation works with a combination of lubricating the TBM shield using bentonite," Arora added.
The 14.57-km tunnel on the 125-km Rishikesh-Karnaprayag Rail Link Project achieved a breakthrough on April 16 in the presence of Railway Minister Ashwini Vaishnaw, Uttarakhand Chief Minister Pushkar Singh Dhami and other railway and state officials.
Live Events
Devprayag-Janasu tunnel, besides being the longest, was completed with the fastest speed in the world. It was for the first time that a Single Shield Hard Rock TBM of 9.11-metre diameter was used in the Himalayas to excavate the mountains.
According to the
Rail Vikas Nigam Limited
(RVNL), out of 14.57 km, 10.49 km was completed through TBM and the rest with the traditional drill and blast method.
"The 9.69-metre diameter Cabrera tunnel in Spain was built by a Double Shield Tunnel Boring Machine (TBM) at an average rate of 423 metres per month and the 10.49-km Devprayag-Janasu tunnel has been completed by Single Shield TBM at an average rate of 413 metres per month, becoming the second fastest in the world," RVNL Chairman and Managing Director Pradeep Gaur had told PTI on the day breakthrough was achieved.
"As the Himalayas are the most challenging geologically, it makes the whole project extremely demanding and interesting. Out of a total of 125 km, 105 km pass through the tunnels.
"Around three km are covered through bridges and four km by adits (openings) and cross passages; the left portion is just 12 to 13 km which consists of 12 station yards," Gaur added.
Arora said the TBM's biggest enemies are water ingress and soft squeezing rock which try to obstruct them from digging a tunnel in the Himalayas. Once a TBM is stuck inside a tunnel, the project is abandoned, he added.
According to L&T officials, besides the state-of-the-art TBM machine, multiple scientific and physical investigations helped them ascertain what kind of rocks they would get ahead and they made preparations accordingly.
"There is a manual probe through drilling and studying the speed of drilling to find out the rock conditions up to 60 metres ahead. Hard rock gives us slow penetration while soft rocks make penetration faster," Arora said.
"The scientific method is Tunnel Seismic Prediction (TSP) in which seismic waves are emitted and a report is prepared on the condition of rocks ahead by studying the speed of the waves. TSP tells us what kind of rock is 100 metres ahead of TBM and 15 metres on both sides of TBM," he said.
The construction firm said they used another physical method to know the rock conditions by investigating the excavated muck.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Over 1.32 Lakh Seats Allotted in Vidarbha as Maharashtra's FYJC Admissions Begin
Over 1.32 Lakh Seats Allotted in Vidarbha as Maharashtra's FYJC Admissions Begin

Time of India

time2 hours ago

  • Time of India

Over 1.32 Lakh Seats Allotted in Vidarbha as Maharashtra's FYJC Admissions Begin

Nagpur: The Maharashtra school education department is set to begin the First-Year Junior College (FYJC) admission process under CAP Round 1 from July 1, with nearly 33% of seats allotted in Vidarbha—marginally higher than the state average of around 30%. Students will have about a week to complete the admission formalities. For the first time in Maharashtra, Class 11 admissions are being conducted on the same online platform where the merit list was declared, which was released on Saturday. In the Vidarbha region comprising Nagpur and Amravati divisions, 1,32,708 seats have been allotted out of 4,08,490 available, reflecting an allotment rate of 32.5%. This indicates that nearly two-thirds of the seats remain open for future rounds, offering students greater flexibility and choice in the upcoming stages. Among the three academic streams, science emerged as the most preferred option. Of the 1,85,275 science seats available in Vidarbha, 75,445 were allotted, showing a fill rate of 40.7%. The arts stream followed with 44,348 allotments from 1,61,435 seats, resulting in a 27.5% fill rate. Commerce remained the least sought-after stream, with only 12,915 of 61,780 seats allotted—a low fill rate of just 20.9%. A district-wise analysis reveals that the Amravati division slightly outperformed the Nagpur division in terms of allotments. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like local network access control Esseps Learn More Undo In the Amravati division, which includes Akola, Amravati, Yavatmal, Buldhana, and Washim, 65,653 students secured seats from a pool of 1,91,075, reflecting a 34.4% allotment rate. In comparison, the Nagpur division, comprising Nagpur, Gondia, Bhandara, Wardha, Chandrapur, and Gadchiroli, saw 67,055 allotments out of 2,17,415 seats, marking a slightly lower allotment rate of 30.9%. Students can check their allotment status online at and must complete document verification and confirm their admission by July 7. Round 2 of the CAP process is expected to begin on July 9, with the next merit list and details of vacant seats to be released shortly thereafter.

Decade-Old Parking Projects Still Stalled At New Friends Colony, Jangpura
Decade-Old Parking Projects Still Stalled At New Friends Colony, Jangpura

Time of India

time2 hours ago

  • Time of India

Decade-Old Parking Projects Still Stalled At New Friends Colony, Jangpura

New Delhi: Seventeen years after the proposal was placed, work on multilevel parking facilities at New Friends Colony and Jangpura still remains incomplete. The facilities, envisioned to ease traffic congestion in the nearby areas, were proposed in 2008 and allotted to a contractor before the 2010 Commonwealth Games. While the facility at New Friends Colony is partially functional, the Jangpura unit is yet to become operational. At the New Friends Colony facility, which was meant to house over 405 vehicles, only two of the three basements are operational, reducing its capacity to around 350. The third basement remains unusable due to perpetual waterlogging caused by high groundwater levels and an active aquifer. "We come around 1 pm daily to collect and drain the water through a pipe," said Bhagwan Prasad Meena, MCD's pump operator. To manage the collected water, MCD has dug a pit nearby, intended for use in watering plants. However, with the monsoon fast approaching, this temporary fix is becoming useless, as the pit could overflow with rainwater before the system is fully in place. You Can Also Check: Delhi AQI | Weather in Delhi | Bank Holidays in Delhi | Public Holidays in Delhi Safety concerns at the site are also pressing, with water bottles and toys strewn across the third basement, which is perennially flooded. Exits at the facility are either broken or left unlocked, and the staircase to the third basement is completely unlit. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like 2025 Top Trending Local Enterprise Accounting Software [Click Here] Accounting ERP Click Here Undo Children playing in the adjacent playground often venture down to retrieve balls. "This is the only playground close to our house," they said when asked why they risked entering the dark and unsafe space. Meanwhile, the Jangpura parking lot, designed for over 300 vehicles, has been closed for more than two years. No construction activity is underway at the three-storey parking facility. "The parking lot has been shut…with no work happening at all. The colony residents are forced to park in front of our shops, causing daily inconvenience," said Mohammad Shoaib, vice-president of the traders' association at Guru Nanak Market, Jangpura. With no designated parking, residents and tenants park haphazardly around the closed facility, exceeding the saturation point. Amit Kaushik, general secretary of Jangpura RWA, blamed the delay on a payment dispute. "The construction has been stalled due to the strife between MCD and the contractor… With the new standing committee chairperson elected, we hope a fresh tender will be issued to complete the work." He also cited a Delhi High Court order dated Nov 11, 2023, which directed MCD to "take appropriate measures to ensure construction and completion within a period of six months from today." An MCD official said, "With the new standing committee in place, we expect a fresh approach within the next 10 days. The pending work at these parking lots will be addressed through the private public partnership method."

Bhagya Nagar Sri Mahankali Bonala Utsavala Ummadi Devalayala Uregimpu Committee offers special Bangaru Bonam to Goddess Kanaka Durga
Bhagya Nagar Sri Mahankali Bonala Utsavala Ummadi Devalayala Uregimpu Committee offers special Bangaru Bonam to Goddess Kanaka Durga

Time of India

time3 hours ago

  • Time of India

Bhagya Nagar Sri Mahankali Bonala Utsavala Ummadi Devalayala Uregimpu Committee offers special Bangaru Bonam to Goddess Kanaka Durga

Vijayawada: The Bhagya Nagar Sri Mahankali Bonala Utsavala Ummadi Devalayala Uregimpu Committee offered a special Bangaru Bonam (Gold Bonam) to Goddess Kanaka Durga on Sunday, continuing their tradition for the 16th consecutive year. The sacred offering was made at the hill shrine on Indrakeeladri, symbolising the strong cultural bond between Telangana and Andhra Pradesh. Committee members began the day by performing special pujas and preparing the Bonam at Jammi Dhoddi Choultry at the foot of the hill. A colourful procession followed, showcasing five traditional Telangana folk art forms, including Pothuraju dance, Garaga Nruthyam, Bethala dance, and others. Women devotees carrying Bonam pots on their heads danced with devotion, while also performing Ganga Puja at the Krishna River near Durga Ghat. The procession was welcomed at the temple by endowments minister Anam Ramanarayana Reddy and Executive Officer Seena Nayak, who formally received the Bonam on behalf of the temple. Gopishetty Raghavender, President of the Bonala Committee, said, "Though we belong to different states now, our devotion is united. by Taboola by Taboola Sponsored Links Sponsored Links Promoted Links Promoted Links You May Like เทรดทองCFDs กับโบรกเกอร์ที่เชื่อถือได้ | เรียนรู้เพิ่มเติม IC Markets สมัคร Undo We see Kanaka Durga as Mahankali's sister and have brought this special Gold Bonam as a token of our love. " Massive devotee turnout on Sunday Being a weekend and part of the Ashadha month, thousands of devotees from both Telugu states gathered at the Durga temple to offer their Saare (ritual offerings). Temple EO Seena Nayak personally monitored the situation to manage the crowd. With increasing rush, the ₹500 special darshan was cancelled, and arrangements were made for quicker darshan for general devotees. Alternate queue lines and designated routes were set up for Saare Samarpana teams, who were also offered free prasadam and blessings on the 6th floor of Maha Mandapam. Many devotees also took part in spiritual rituals like Suryopasana, Chandi Homam, and Laksha Kumkumarchana.

DOWNLOAD THE APP

Get Started Now: Download the App

Ready to dive into a world of global content with local flavor? Download Daily8 app today from your preferred app store and start exploring.
app-storeplay-store