Contractors liable for defects at Pasir Gudang Hospital, says PWD

The Sun15 hours ago

JOHOR BAHRU: Contractors involved in the Pasir Gudang Hospital (HPG) project remain responsible for addressing defects during the liability period, Public Works Department (PWD) director-general Datuk Roslan Ismail said today.
Despite the hospital's handover to the Health Ministry (MoH) on June 12, contractors must rectify any issues reported during the defects liability period as per contract terms.
'Contractors must continue to fulfill their obligations throughout the defects liability period as stipulated in the contract.
Therefore, I would like to remind contractors to carry out preventive maintenance according to schedule and to act promptly and responsively in addressing and rectifying any complaints,' Roslan said during the handover ceremony.
Health Minister Datuk Seri Dr Dzulkefly Ahmad was also present.
Originally scheduled for completion on Sept 15, 2024, the RM375.5 million project was finished ahead of time. Site possession began on Sept 15, 2020, with the Certificate of Completion and Compliance (CCC) issued on May 27 and the Certificate of Practical Completion (CPC) on June 12.
Roslan credited the project's success to stakeholder collaboration despite challenges like COVID-19 disruptions.
The hospital, built using the Design and Build method, adheres to Environmental, Social and Governance (ESG) principles for sustainability.
With 304 beds and 14 specialist services, the hospital aims to ease congestion at Hospital Sultanah Aminah (HSA) and Hospital Sultan Ismail (HSI).
Facilities include a main hospital block, staff quarters, a nurses' dormitory, and over 1,500 parking bays.

Orange background

Try Our AI Features

Explore what Daily8 AI can do for you:

Comments

No comments yet...

Related Articles

Hospital Pasir Gudang to start operating in phases from Aug 1
Hospital Pasir Gudang to start operating in phases from Aug 1

Malaysian Reserve

time11 hours ago

  • Malaysian Reserve

Hospital Pasir Gudang to start operating in phases from Aug 1

JOHOR BAHRU — Hospital Pasir Gudang (HPG), which was officially handed over to the Ministry of Health (MOH) today, will begin operating in phases from Aug 1, said Health Minister Datuk Seri Dr Dzulkefly Ahmad. He said the initial phase would involve 30 per cent of core services, including Accident and Emergency (A&E), Obstetrics and Gynaecology, and the Paediatric Department. 'So far, 274 positions have been filled, and we expect to be fully operational with 1,845 staff by July 2026,' he told a press conference after attending the HPG project handover ceremony here today. Also present was Public Works Department director-general Datuk Roslan Ismail. Dzulkefly said that with a capacity of over 300 beds, HPG would help reduce the workload at Johor Bahru's two main hospitals – Hospital Sultanah Aminah (HSA) and Hospital Sultan Ismail (HSI) – particularly in handling emergency cases and stable patients. He said this was in line with Johor's projected population growth, which was expected to reach 3.90 million by 2025, up from 3.35 million in 2010, with an annual growth rate of two per cent, particularly in Johor Bahru. Earlier in his speech, Dzulkefly said HPG was the first hospital to offer around 20 on-call suites for specialist doctors as part of efforts to safeguard their welfare and ensure staff comfort. He said that during its construction, HPG consistently remained ahead of schedule and was never listed among delayed or 'sick' projects, despite the challenges posed by the Movement Control Order (MCO). 'HPG has become a benchmark for meticulous planning and integrated implementation that has realised the people's hopes,' he said. Dzulkefly said the opening of HPG brought the total number of specialist hospitals in Johor to eight and this was expected to ease congestion at HSA by reducing its bed occupancy rate by five to 10 per cent within two years through the transfer of stable patients. 'With the full operation of HPG, the waiting time for elective surgery services at HSA is expected to be reduced by 30 per cent within the first two years,' he said. –BERNAMA

Pasir Gudang Hospital to operate in stages starting Aug 1
Pasir Gudang Hospital to operate in stages starting Aug 1

New Straits Times

time12 hours ago

  • New Straits Times

Pasir Gudang Hospital to operate in stages starting Aug 1

PASIR GUDANG: Pasir Gudang Hospital (HPG), built at a cost of RM500 million, will begin operations in phases starting Aug 1. It is the third public hospital in Johor Baru, after Sultanah Aminah Hospital (HSA) and Sultan Ismail Hospital (HSI). Health Minister Datuk Seri Dr Dzulkefly Ahmad said the new facility is expected to ease congestion at HSA and HSI once it becomes fully operational by July next year. "Operations at HPG will begin in phases from Aug 1, starting with 30 per cent of its core services. "These include General Medicine, Nephrology, Emergency and Trauma Services (ETS), Paediatrics, Obstetrics and Gynaecology (O&G), and surgical care. "The Health Ministry aims for the hospital to be fully operational by July 2026, supported by over 1,800 staff. This will significantly ease congestion at both HSA and HSI. "Specialists have already started taking up their posts here, particularly in key departments, in preparation for the opening," he told reporters after the Pasir Gudang Hospital Project Handover Ceremony held here today. Present were Health Ministry secretary-general Datuk Seri Suriani Ahmad; Public Works Department director-general Datuk Roslan Ismail; Johor Health and Environment Committee chairman Ling Tian Soon; and Johor Public Works, Transport, Infrastructure and Communications Committee chairman Mohamad Fazli Mohamad Salleh. Located in Bandar Seri Alam and spanning 20.6 hectares, HPG is equipped with 304 beds and offers 14 specialist services. Its facilities include 36 Class G staff quarters, 50 units of nurses' hostel blocks, 1,507 car parking bays, 320 motorcycle bays, and 32 bays for persons with disabilities. Commenting on the proposal to build Sultanah Aminah Hospital 2 (HSA 2) to ease severe congestion at the existing HSA, Dzulkefly said preliminary works have already started. Last month, it was reported that the HSA 2 project had entered the final phase of preparing the working paper, which is expected to be tabled to the Cabinet for further deliberation and approval. Ling was reported as saying that the progress followed the resolution of land ownership issues and the completion of preliminary groundwork. The working paper was expected to be finalised last month. The proposed site for HSA 2 involves part of a land parcel owned by the Defence Ministry in Skudai, which has already granted permission for development. Earlier, the federal government approved funding for initial works through a budget presented by Prime Minister Datuk Seri Anwar Ibrahim.

Pasir Gudang Hospital completed, but contractors still liable for defects
Pasir Gudang Hospital completed, but contractors still liable for defects

New Straits Times

time13 hours ago

  • New Straits Times

Pasir Gudang Hospital completed, but contractors still liable for defects

JOHOR BARU: Contractors have been reminded to respond promptly to any complaints during the defects liability period for the Pasir Gudang Hospital (HPG) project, said Public Works Department (PWD) director-general Datuk Roslan Ismail. He said that although full building management and control had been handed over to the Health Ministry (MOH) following the hospital's completion on June 12, contractors remain responsible for addressing any defects. "Contractors must continue to fulfil their obligations throughout the defects liability period as outlined in the contract. "I urge them to carry out preventive maintenance as scheduled and to act swiftly in responding to and rectifying any complaints," he said at the hospital's handover ceremony today. Also present was Health Minister Datuk Seri Dr Dzulkefly Ahmad. Roslan said the 20.65-hectare hospital was originally scheduled for completion on Sept 15 last year, with a project cost of RM375.5 million following site possession on Sept 15, 2020. The Certificate of Completion and Compliance (CCC) was issued on May 27, followed by the Certificate of Practical Completion (CPC) on June 12. Despite challenges including on-site disruptions and delays due to the COVID-19 pandemic, Roslan said the project was completed with the cooperation of all stakeholders. The hospital, built using the Design and Build method and aligned with Environmental, Social and Governance (ESG) principles, is designed to be sustainable, resilient and environmentally friendly. It will begin phased operations on Aug 1. The hospital is expected to improve healthcare access for local residents, offering 304 beds and 14 specialist services to help ease overcrowding at Sultanah Aminah Hospital and Sultan Ismail Hospital. The project also includes a main hospital block, staff quarters, a nurses' dormitory, plant and support buildings, 1,507 parking bays, 320 motorcycle lots, and 32 parking spaces for people with disabilities. — BERNAMA