Flash floods: Selangor govt to expedite 17 mitigation projects
State Infrastructure and Agriculture Exco Datuk Izham Hashim said the projects would be implemented in 13 identified hotspots, including Meru and Pandamaran.
He said the projects to be implemented include drain widening works, installation of culverts for waterways, upgrading bridges involving village areas as well as pocket development.
"Some of these projects will be started as early as this week and are expected to be completed by October, with an estimated RM3 million allocated for the implementation of these 17 immediate projects.
"The implementation of these 17 projects will be brought to the Selangor Economic Action Meeting (MTES) within two weeks from now there are several projects involving the implementation of state government policies," he told reporters after chairing a Meeting to Discuss Infrastructure Progress for MBDK's supervised areas at the MBDK Headquarters here today.
Izham said all the projects would be coordinated by the Selangor Irrigation and Drainage Department (DID) in collaboration with several other agencies including MBDK and the Public Works Department (PWD).
He said the projects were an effort by the state government to reduce flood incidents, especially flash floods which frequently occur while waiting for the Flood Mitigation Plan in the Klang area to be fully completed.
Apart from the immediate measures project, a total of 15 medium-and long-term flood mitigation projects involving the federal government were also implemented with funds of nearly RM45 million, he said.
Meanwhile, Izham said DID also identified more than 300 unmanned catchment ponds and was one of the factors that caused floods to occur due to improper maintenance.
He said following this, DID was in the process of taking over the ponds in stages and currently, about 55 ponds have been taken over.
Hashtags

Try Our AI Features
Explore what Daily8 AI can do for you:
Comments
No comments yet...
Related Articles


The Star
3 days ago
- The Star
MyKiosk placements in Selangor under review
SHAH ALAM: Local authorities across Selangor are being urged to reassess the placement of MyKiosk units, amid growing concerns that they pose safety hazards and fail to attract the intended traders and customers. Selangor's local government and tourism committee chairman, Datuk Ng Suee Lim, announced that local authorities have been given three months to monitor the situation. "If local authorities find the placement of MyKiosk is unsuitable—either obstructing pedestrian walkways or not attracting customers—they can relocate the kiosks," he said during the Selangor State Assembly sitting on Wednesday (July 9). Ng observed that some successful applicants are merely "a flash in the pan," as they either operate the kiosks for a short time or occupy them without sincere commitment. "If such situations persist for several months, we might consider replacing the operator," he added, noting the Housing and Local Government Ministry (KPKT) is targeting a 90% occupancy rate by August. He was responding to Dr Afif Bahardin (PN-Taman Medan), who asked about efforts to fill MyKiosks given the low occupancy over the past year. Dr Afif highlighted resident complaints about empty kiosks becoming mosquito breeding grounds, obstructing pathways, and the prohibitive deposit of RM2,000 to RM3,000 deterring applicants. Ng said he would review the deposit rate but explained that deposits are necessary to ensure traders maintain their kiosks. "Commitment from operators to care for MyKiosk is part of the cooperation between traders and local authorities," he explained. In response to Dr Afif's inquiries about the number of MyKiosk units and the budget, Ng reported that 1,028 MyKiosk units, costing RM20.33mil, have been distributed across Selangor. "Taman Medan has the most units at 123, followed by Kota Damansara with 85 and Kota Anggerik with 75 units," he said. Of the total cost, RM19,508,520.56 was funded by a ministry allocation. The remaining RM822,211 was covered by local authorities for site preparation, tailored to each location's specific conditions. On average, constructing a MyKiosk unit costs RM19,785.80, including structure and site preparation. "The MyKiosk initiative provides better, cleaner, and more organised facilities for traders and addresses issues like hawkers trading in high-risk or unsuitable locations such as roadsides and pavements, which contribute to traffic congestion and safety issues," said Ng. "It also expands entrepreneurial opportunities for small-scale traders, micro-entrepreneurs, and low-income communities."


The Sun
5 days ago
- The Sun
Hulu Langat flood mitigation project enters detailed design phase
SHAH ALAM: The Selangor State Legislative Assembly received an update on the progress of the Hulu Langat Flood Mitigation Project Phase 2, which has now entered the detailed design phase. State Infrastructure and Agriculture Committee chairman Datuk Izham Hashim confirmed that the project will proceed to land acquisition and utility relocation once the design is finalised, with physical construction expected to commence in 2027. The project spans multiple areas, including Kajang town, Kampung Sungai Serai, Kampung Sungai Lui, Kampung Dusun Tua, Taman Sri Nanding, Taman Sri Jelok, and Kampung Sungai Kantan. Key components involve river deepening, embankment construction, water gate installation, pump systems, and water retention ponds. Datuk Izham provided these details in response to an oral question from Datuk Johan Abd Aziz (BN-Dusun Tua) regarding the status of the flood mitigation plan. The initiative falls under the 12th Malaysia Plan (12MP) and includes Phase 2, Package 1 of the Sungai Langat Flood Mitigation Plan in Hulu Langat District, backed by a RM512 million budget allocation. - Bernama

Barnama
5 days ago
- Barnama
Detailed Design Underway For Hulu Langat Flood Mitigation Plan
SHAH ALAM, July 7 (Bernama) -- The Selangor State Legislative Assembly was briefed today on the progress of the Hulu Langat Flood Mitigation Project Phase 2, now in the detailed design phase. State Infrastructure and Agriculture Committee chairman Datuk Izham Hashim said once the design phase is complete, the project will proceed with land acquisition and utility relocation before physical construction begins, which is expected to start in 2027. 'The project covers several areas, including Kajang town, Kampung Sungai Serai, Kampung Sungai Lui, Kampung Dusun Tua, Taman Sri Nanding, Taman Sri Jelok, and Kampung Sungai Kantan. 'The work involves river deepening, constructing embankments and water gates, as well as installing pumps and building water retention ponds,' he said during the assembly sitting here today. He was responding to an oral question from Datuk Johan Abd Aziz (BN-Dusun Tua) regarding the status of the Hulu Langat flood mitigation plan. The project, part of the 12th Malaysia Plan (12MP), entails the construction of Phase 2, Package 1 of the Sungai Langat Flood Mitigation Plan in Hulu Langat District, with a budget allocation of RM512 million. -- BERNAMA